Back to ArticlesBack

Join 50,000+ PM Professionals

Get expert PM insights, PMP prep tips, and earn PDUs with exclusive content delivered weekly.

Protected by reCAPTCHA: Privacy & Terms

MPUG - Master Project User GroupMPUG - Master Project User Group

Problem

One of the challenges facing project managers who use the Microsoft PPM solution (Project Online or Project Server) is how to prevent team members from entering additional time on completed tasks. For example, two weeks ago a team member named Mickey Cobb used the Timesheet page in Project Web App to enter time on a task. The time she entered resulted in the completion of the task. Two weeks later, Mickey performs work that does not coincide with any task to which she is assigned. Being a dutiful team member, Mickey wants to enter time somewhere, so she enters the time on the task she completed two weeks earlier. This is not a good practice and should be prevented. Fortunately, Microsoft offers us two different method for locking completed tasks.

Solution

One way to prevent team members from entering additional time on a completed task is to use a feature that has been in Project Web App for many years: the Locked column. To lock a task using this feature, the project manager must do the following:

    1. Log into Project Web App with Project Manager permissions.
    2. Navigate to the Project Center
    3. Click the name of an enterprise project to open it as Read-Only in a web view.
    4. In the “drill down” section at the top of the Quick Launch menu, click the Schedule link to display a detailed view of the project.
    5. Click the Task tab to expand the Task
    6. In the Project section of the Task ribbon, click the Edit pick list button and select the In Browser item to check out the project for editing in your browser, as shown in Figure 1.

Figure 1: Check out the project for editing

7. In the Data section of the View ribbon, click the View pick list button and select the Close Tasks to Update view, as shown in Figure 2. This view includes the Locked column that you can use to prevent team members from entering additional time on completed tasks.

Figure 2: Select the Close Tasks to Update view

8. Set the Locked value to Yes for every detail task that is 100% complete, as shown in Figure 3. A detail task is any task with resources assigned. You do not need to specify a Locked value for summary tasks and milestone tasks.

Figure 3: Set the Locked value to Yes

9. In the Project section of the Task ribbon, click the Publish

10. When the publish job is completed, click the Close button in the Project section of the Task

11. When prompted in a confirmation dialog, leave the Check it in value selected and then click the OK

As you can see from the previous set of steps, it is a lengthy process to lock completed tasks using this method. To our benefit, however, Microsoft recently introduced a new feature to speed up this process by allowing you to use the Locked column in Microsoft Project. To lock a task using this new feature, the project manager must complete the following steps:

  1. Launch Microsoft Project Professional and connect to Project Web App in the Login
  2. Open an enterprise project and check out the project for editing.
  3. Apply any task view, such as the Gantt Chart view, for example.
  4. Right-click on the column header of any column, such as the Duration column, and then select the Insert Column item on the shortcut menu.
  5. In the list of available task columns, select the Locked
  6. Set the Locked value to Yes for every detail task that is 100% complete, as shown in Figure 4.
  7. Save and publish the enterprise project, then close and check in the project.

I think you can see that the process for locking completed tasks is much simpler using the Microsoft Project desktop client than it is using the Project Web App user interface. Using either method will prevent your team members from adding time to each task you lock.


Related Content

Webinars (watch for free now!):
Advanced Tips for Resolving Resource Over/Underallocation
Eliminate the Confusion – Deep Dive into Task Types and Effort Driven

Articles:
Exploratory vs. Explanatory Visuals in Planning
Microsoft Project Do’s and Don’ts: Enter Task Durations
When a Fixed Duration Task is Truly Not “Fixed Duration”


Get Weekly PM Insights

Join 50,000+ PMs receiving updates on the latest PM methodologies, PDU opportunities, tool reviews, career tips, and member exclusives.

Protected by reCAPTCHA: Privacy & Terms

PMI ATP
PMI Authorized Training Partner
REP #4082

Learning Paths

PMP® TrainingCAPM® TrainingPgMP® TrainingPMI-ACP® TrainingMS ProjectMS PlannerMS TeamsJira

PM Resources

PDU TrackerLive WebinarsSalary CalculatorTool ComparisonsJob BoardKnowledge BasePM Glossary

Community

Discussion ForumStudy GroupsEvents Calendar

Follow Us

LinkedInYouTubeTwitterFacebook
MPUG Logo

© 2026 MPUG. All rights reserved.

TermsPrivacySitemapAdvertise
Articles

Using the Locked Column to Prevent Task Updates

Problem One of the challenges facing project managers who use the Microsoft PPM solution (Project Online or Project Server) is how to prevent team members from entering additional time on […]

4 min read
•over 8 years ago•Updated 3 months ago•
D
Dale HowardAuthor
Project Management
Microsoft Project
Best Practices
Productivity
D
Dale Howard

Content Writer

Dale Howard is currently a Senior PPM Consultant with Arch Systems, Inc. His hair and beard have turned white because of using Microsoft's project management tools for more than 20 years. Dale started his career using Microsoft Project 4.0 for Windows 95 and began using Microsoft's PPM tools when they introduced Project Central in 2000. Dale is the co-author of 23 books in Microsoft Project, Project Server, and Project Online. He is currently one 0f 26 Microsoft Project MVPs in the entire world and one of only 4 Project MVPs in the United states.

View all articles by Dale Howard
Related Content

Continue Reading

Discover more insights and articles that complement your current reading

The Toilet Paper Rule: Why Small Problems Become Big Failures
Articles
1 min read

The Toilet Paper Rule: Why Small Problems Become Big Failures

Ronald B. Smith uses the humble toilet paper roll to unpack six enduring truths about preparation, quality, and the invisible work of project management.

A
Anonymous
2 days ago
Read
Are You Running a Risk Meeting or a Risk Workshop?
Articles
1 min read

Are You Running a Risk Meeting or a Risk Workshop?

Learn the difference between a risk meeting and a risk workshop, and why structured risk workshops help project teams identify owners, define actions, and protect project outcomes.

A
Anonymous
9 days ago
Read
“I Need a Dashboard by Friday” – How AI Just Made That Possible
Articles
1 min read

“I Need a Dashboard by Friday” – How AI Just Made That Possible

Need a dashboard by Friday? Discover how AI tools like ChatGPT can help you build an Excel dashboard quickly and easily—no advanced technical skills required. Learn how to turn plain-English requests into real, working reports with spreadsheets that actually work for you.

A
Anonymous
9 days ago
Read
Explore All Articles