Reports, Views, Tables and Visual Reports all give you great options for communicating project information. They also require time to explore and configure. But there is one reporting tool within Microsoft Project designed to give you on-demand status, that requires no configuration and that’s perfect for keeping historical information.

I want to show you the Project Statistics dialog box and how to use it in making a project journal — a readable, visual history of progress and of learning. Find Project Statistics by first selecting Project from the menu, and then Project Information. See Figure 1.

Figure 1: Open Project Information from the Project menu item.

The 30-second Report

At the bottom of Project Information, click on the Statistics button. See Figure 2.

Figure 2: Click on the Statistics button.

The 30-second Report

This action brings up Project Statistics for your review. Please note that this information is the current status of your Project file. See Figure 3.

Figure 3: Project Statistics offers you the status of the project.

The 30-second Report

Note how much information is listed! While small, this dialog box is also packed with information you need to know, particularly if you’re evaluating progress or documenting the evolution of the project. Pasting this information into a word processor prior to entering updates and then again after making updates allows you to easily compare them and evaluate the differences.

To copy Project Statistics into your word processor, you must first copy it onto Windows Clipboard. You copy the dialog box onto the Clipboard by first ensuring Project Statistics is the active window, then by pressing Alt-Print Screen on your keyboard. Paste the data into the word processor with Ctrl-V.

Once the Project Statistics are in your word processor, you can make comments explaining the difference. Here’s an example that explains the difference between Figures 3 and 4: “There was a delay of work during the Thanksgiving holiday of 6 days. Costs are stable as is the amount of work, but the schedule has slipped over a week due to the delay.”

Figure 4: Status after the delay.

The 30-second Report

I recommend you try this 30-second reporting technique for a new perspective on project documentation. It allows you easily to create and keep a visual running history of your project.

Get Weekly PM Insights

Join 500,000+ PMs receiving updates on the latest PM methodologies, PDU opportunities, tool reviews, career tips, and member exclusives.

PMI ATP
PMI Authorized Training Partner
REP #4082

Learning Paths

PMP® TrainingCAPM® TrainingPgMP® TrainingPMI-ACP® TrainingMS ProjectMS PlannerMS TeamsJira

PM Resources

PDU TrackerLive WebinarsSalary CalculatorTool ComparisonsJob BoardKnowledge BasePM Glossary

Community

Discussion ForumStudy GroupsEvents Calendar

Follow Us

LinkedInYouTubeTwitterFacebook
MPUG Logo

© 2025 MPUG. All rights reserved.

TermsPrivacySitemap
Articles

The 30-second Report

Reports, Views, Tables and Visual Reports all give you great options for communicating project information. They also require time to explore and configure. But there is one reporting tool within […]

2 min read
•almost 17 years ago••
S
Sam HuffmanAuthor
Project Management
Microsoft Project
Best Practices
Productivity
S
Sam Huffman

Content Writer

Sam Huffman first gained insight into Microsoft Project while working as a member of the MS Project development and support team. He has maintained his depth of knowledge of MS Project with each release and is a leading authority in the use and features of MS Project, Project Server and Project Online. Since the early 1990's Sam has honed his instruction skills by delivering training programs to thousands every year. Sam is a frequent content contributor to the Microsoft Project User Group (MPUG) and speaks to groups often about MS Project, Enterprise Project Management and the discipline of Project Management. He was awarded Microsoft Most Valuable Professional from 2010-2017. Check out his blog on MS Project. The softcover version of my newest book Microsoft® Project Do’s and Don’ts is now available for purchase! It is portable, brief and to the point so you can find help when you need it. Through tips, best practices and examples it will help you jumpstart your project!

View all articles by Sam Huffman
Related Content

Continue Reading

Discover more insights and articles that complement your current reading

Two Project Manager Agent Features You Might Like
Articles
5 min read

Two Project Manager Agent Features You Might Like

Discover two game-changing features of Microsoft’s Project Manager Agent including agent-to-agent communication and the new integrated interface in Planner.

E
Erik van Hurck
about 1 month ago
Read
Master Dependency Analysis in Microsoft Project with SSI Tools!
Articles
2 min read

Master Dependency Analysis in Microsoft Project with SSI Tools!

Learn how to master dependency analysis in Microsoft Project using SSI Tools’ Directional Path, Connecting Path, and Dependency Tracer to analyze predecessors, successors, and project logic.

K
Kenny Arnold
about 1 month ago
Read
A PM’s Halloween Survival Guide
Articles
5 min read

A PM’s Halloween Survival Guide

Discover the spooky parallels between Halloween and project management, from scope creep monsters to ghosted team members, in this fun survival guide for PMs.

R
Ronald B. Smith, MBA, PMP
about 2 months ago
Read
Explore All Articles