Back to ArticlesBack

Join 50,000+ PM Professionals

Get expert PM insights, PMP prep tips, and earn PDUs with exclusive content delivered weekly.

MPUG - Master Project User GroupMPUG - Master Project User Group

A user posed an interesting question recently in the Microsoft Project Standard and Professional TechCenter forum on the Internet. He asked how to assign resources to a task to generate the shortest Duration possible for the task using the following requirements:

  • The task requires 100 hours of total work for all assigned resources.
  • One resource is available to work full-time and should be assigned at a Units value of 100 percent.
  • Two other resources are available to work only half-time and should each be assigned at a Units value of 50 percent.

The Solution

The solution to this problem isn’t difficult, but it does require a series of specific steps to force Project to calculate the shortest Duration for the task. Here are the required steps:

  1. Apply the Gantt Chart view.
  1. Reset the Duration of the task to the default value of 1 day, if necessary.
  1. Right-click anywhere in the Gantt Chart pane on the right side of the view and select the Show Split item on the shortcut menu, as shown in this screenshot:

This action applies a combination or “split” view, known as the Task Entry view. The Task Entry view includes the Gantt chart view in the top pane and the Task Form view in the bottom pane.

  1. Select the task in question in the task list on the left side of the Gantt Chart pane.
  1. In the Task Form pane, make sure the Task Type value is set to Fixed Units. If not, select Fixed Units and click the OK button.
  1. In the Task Form pane, make sure the Effort driven checkbox is selected. If not, select it, and then click the OK button. The following figure shows the Task Entry view with the correct settings for the selected the task.

  1. In the Resource Name column of the Task Form pane, select the name of the resource who can work full-time.
  1. For this selected resource, enter 100% in the Units column and 100h in the Work column and click OK. Project should calculate an initial Duration value of 12.5 days for the task, as shown in this figure:

  1. Below the name of the first resource you selected in the Task Form pane, select the names of the two other resources who will be working half-time.
  1. For each of these two resources, enter 50% in the Units column.
  1. Click the OK button ONLY AFTER you have selected the two other resources.

This final step should reduce the Duration to 6.25 days, allocate 50 hours of work to the full-time resource, and allocate 25 hours of work to each of the two half-time resources. The result is the shortest Duration possible for the task, based on the work and resource requirements, as shown here:

You can see from the previous steps that the answer to this question was straightforward, but not exactly simple. The trick was to use the Effort driven capabilities of Project to allocate the 100 hours of planned work in the most efficient manner between the assigned resources, so that the software would calculate the shortest Duration for the task.

A version of this article originally appeared on the Sensei Project Solutions blog.

Have your own tricks? Share them with the MPUG community by writing an article! Contact editor@MPUG.com to learn more.

Image Source

Get Weekly PM Insights

Join 50,000+ PMs receiving updates on the latest PM methodologies, PDU opportunities, tool reviews, career tips, and member exclusives.

PMI ATP
PMI Authorized Training Partner
REP #4082

Learning Paths

PMP® TrainingCAPM® TrainingPgMP® TrainingPMI-ACP® TrainingMS ProjectMS PlannerMS TeamsJira

PM Resources

PDU TrackerLive WebinarsSalary CalculatorTool ComparisonsJob BoardKnowledge BasePM Glossary

Community

Discussion ForumStudy GroupsEvents Calendar

Follow Us

LinkedInYouTubeTwitterFacebook
MPUG Logo

© 2026 MPUG. All rights reserved.

TermsPrivacySitemap
Articles

Scheduling the Shortest Duration Possible

A user posed an interesting question recently in the Microsoft Project Standard and Professional TechCenter forum on the Internet. He asked how to assign resources to a task to generate […]

3 min read
•over 8 years ago•Updated 15 days ago•
D
Dale HowardAuthor
Project Management
Microsoft Project
Best Practices
Productivity
D
Dale Howard

Content Writer

Dale Howard is currently a Senior PPM Consultant with Arch Systems, Inc. His hair and beard have turned white because of using Microsoft's project management tools for more than 20 years. Dale started his career using Microsoft Project 4.0 for Windows 95 and began using Microsoft's PPM tools when they introduced Project Central in 2000. Dale is the co-author of 23 books in Microsoft Project, Project Server, and Project Online. He is currently one 0f 26 Microsoft Project MVPs in the entire world and one of only 4 Project MVPs in the United states.

View all articles by Dale Howard
Related Content

Continue Reading

Discover more insights and articles that complement your current reading

How Reserves Keep Projects Alive
Articles
4 min read

How Reserves Keep Projects Alive

Learn how project reserves protect your budget and schedule from unexpected risks, including when and how to use contingency, management, schedule, and cost reserves effectively.

R
Ronald B. Smith, MBA, PMP
11 days ago
Read
Why Platform Migrations Fail (And How to Land Yours Successfully)
Articles
4 min read

Why Platform Migrations Fail (And How to Land Yours Successfully)

Learn why platform migrations fail and how to land yours successfully using proven change management tactics for PMOs facing tool transitions like Project Online’s retirement.

T
The MPUG Community
14 days ago
Read
Beyond Project Online: Why Now Is the Time to Plan Your Move to Modern Portfolio Management and How We Can Help
Articles
5 min read

Beyond Project Online: Why Now Is the Time to Plan Your Move to Modern Portfolio Management and How We Can Help

Microsoft Project Online retires September 2026. Learn why now is the time to plan your transition to modern portfolio management and join our free webinar on January 28.

T
The MPUG Community
25 days ago
Explore All Articles
Read