Unless you have been living in a cave, you will have heard that May 2010 sees the virtual launch of Office 2010. But I thought Id take a few minutes to prepare the scene.I know you will read the wealth of documentation we have up on the TechNet Project Server 2010 TechCenter, but sometimes our customers can get imaginative and read more into what we don’t say than what we do.”I know TechNet says that apples are apples, but it doesn’t say that apples are not bananas!”

So to remove the cover off of the things that have caught some of our internal folks and early adopters out…

  • You need to have SharePoint Server 2010 licensed as ENTERPRISE to be able to load and run Project Server 2010
    • It will NOT run or load on SharePoint Foundation, SharePoint server 2007, WSS 3.0, SharePoint Portal Server 2003, SharePoint Team Services, Office Web Folders (yes, I have been around SharePoint that long…) or any earlier variant of FPSE or VTI stuff.
    • You cannot use SharePoint 2010 (any version) to support Project Server 2007 or earlier.
  • You need x64, for ALL servers.
  • You need x64 for your SQL Server. Theoretically I think you could support the Analysis Services features on a different x86 SQL Server, but why would you
    • You cannot use the Analysis Services instance created for PowerPivot to support Project Server 2010 OLAP database functionality — the OLAP mode it requires is not compatible with the mode required for Project. You could use a different instance on the same server — but be aware that PowerPivot has some high resource requirements and might be best on its own server.
  • As you have SharePoint Server on your farm as a requirement, please take into account the extra resource requirements before turning on all the extra new services.
  • If you have a 2007 farm with MOSS and Project Server and you plan to upgrade in place (assuming you meet all the requirements — x64 etc.), then you have to upgrade to both SharePoint Server and Project Server 2010.You cannot just upgrade SharePoint.Also note that October 2009 CU is required as the starting point for this in-place upgrade.
  • Project Professional 2010 can only connect to Project Server 2010.Project Professional 2007 can connect to 2010 servers in Backwards Compatibility mode.
  • If you are running SharePoint PowerShell commands, you need to be running as an administrator.

Apples are not bananas. See full details of the requirements.

Please note the SQL Server requirements particularly:

  • SQL Server 2008 SP1, CU2 or CU5 or above (not CU3 or CU4)
  • SQL Server 2005 SP3, CU3

So start getting your servers or HyperV images prepared — and above all, enjoy!Project Server 2010 is an awesome product, and that is a word I do not use lightly!

This article was first published by Microsoft on the Office Project Support Weblog.

Get Weekly PM Insights

Join 50,000+ PMs receiving updates on the latest PM methodologies, PDU opportunities, tool reviews, career tips, and member exclusives.

Protected by reCAPTCHA: Privacy & Terms

PMI ATP
PMI Authorized Training Partner
REP #4082

Learning Paths

PMP® TrainingCAPM® TrainingPgMP® TrainingPMI-ACP® TrainingMS ProjectMS PlannerMS TeamsJira

PM Resources

PDU TrackerLive WebinarsSalary CalculatorTool ComparisonsJob BoardKnowledge BasePM GlossaryOur Faculty

Community

Discussion ForumStudy GroupsEvents Calendar

Follow Us

LinkedInYouTubeTwitterFacebook
MPUGMaster Project User Group

© 2026 MPUG. All rights reserved.

TermsPrivacySitemapAdvertise
Articles

Project Server 2010: Things to Note, and Avoid, as You Start the 2010 Journey

Unless you have been living in a cave, you will have heard that May 2010 sees the virtual launch of Office 2010. But I thought Id take a few minutes […]

3 min read
•over 16 years ago•Updated 10 months ago•
B
Brian SmithAuthor
Project Management
Microsoft Project
Best Practices
Productivity
B
Brian Smith

Content Writer

Brian Smith is a Senior Support Escalation Engineer in the Microsoft CSS in the Project Support team. He has supported Project and Project Server since the 2002 version, including the Beta programs for 2007 and 2010, and is looking forward to supporting the new Project!

View all articles by Brian Smith
Related Content

Continue Reading

Discover more insights and articles that complement your current reading

An Introduction to the PMI Practice Standard for Scheduling Conformance Index
Articles
1 min read

An Introduction to the PMI Practice Standard for Scheduling Conformance Index

Learn how the Conformance Index in PMI’s Practice Standard for Scheduling scores a CPM schedule model, and how to assess its components in any scheduling tool.

A
Anonymous
6 days ago
Read
A PM’s Halloween Survival Guide: The Sequel You Didn’t Want but Definitely Need
Articles
1 min read

A PM’s Halloween Survival Guide: The Sequel You Didn’t Want but Definitely Need

Part II of the PM Halloween survival guide takes on shape-shifting requirements and dependencies that won’t stay resolved, with practical defenses for each.

A
Anonymous
24 days ago
Read
Context Engineering for Project Managers: Give AI the Project, Not Just the Question
Articles
1 min read

Context Engineering for Project Managers: Give AI the Project, Not Just the Question

Learn how to choose, date, and source the project information you give AI, so its risk analyses, status reports, and change request reviews reflect your actual project.

A
Anonymous
about 1 month ago
Read
Explore All Articles