Sync to SharePoint is a useful feature for those organizations that have SharePoint 2010, but not Project Server 2010 — or for those that have both, but prefer to use a simple SharePoint task list to publish project plans rather than Project Server 2010.

Usage is simple. First, you set up the SharePoint list. In SharePoint 2010, the icon to do so looks like this:

Microsoft Project 2010 Feature Rally: Sync to SharePoint

For illustration purposes I’ve created a task list named “Sync To SharePoint Training Deployment.” Although task list names may generally contain special characters, for the purposes of Sync to SharePoint with your project plan they can’t.

Next I created a very simple project, which is based on the Microsoft template for a training deployment. For the purposes of this article, I’ve deleted many of the tasks to simplify the demonstration.

Microsoft Project 2010 Feature Rally: Sync to SharePoint

In order to synchronize this project to my SharePoint list, I navigate through File | Save & Send | Sync with Tasks List. Now the first thing I do is type In the site collection name of the SharePoint site I want to access. After that I click the Validate URL button. In my case, because the project name was similar to the SharePoint task list name, the correct task list was selected for me in the Select an existing tasks list, or enter a new name drop down list box. Note that I could have chosen to create the SharePoint task list during the sync process; however, the most common scenario based on your organization’s security will probably be the former.

Microsoft Project 2010 Feature Rally: Sync to SharePoint

Now click the Sync button. You may receive a confirmation message during the sync; just click OK when you do. Upon completion you’ll have (I hope!) successfully synchronized your project to the SharePoint task list. Note that summary tasks will show up as folders. When you click on a folder, subtasks will appear.

Microsoft Project 2010 Feature Rally: Sync to SharePoint

Microsoft Project 2010 Feature Rally: Sync to SharePoint

Microsoft Project 2010 Feature Rally: Sync to SharePoint

Of course, there more functionality to be had, but that’ll have to wait for a future article or WebNLearn.

Get Weekly PM Insights

Join 50,000+ PMs receiving updates on the latest PM methodologies, PDU opportunities, tool reviews, career tips, and member exclusives.

Protected by reCAPTCHA: Privacy & Terms

PMI ATP
PMI Authorized Training Partner
REP #4082

Learning Paths

PMP® TrainingCAPM® TrainingPgMP® TrainingPMI-ACP® TrainingMS ProjectMS PlannerMS TeamsJira

PM Resources

PDU TrackerLive WebinarsSalary CalculatorTool ComparisonsJob BoardKnowledge BasePM GlossaryOur Faculty

Community

Discussion ForumStudy GroupsEvents Calendar

Follow Us

LinkedInYouTubeTwitterFacebook
MPUGMaster Project User Group

© 2026 MPUG. All rights reserved.

TermsPrivacySitemapAdvertise
Articles

Microsoft Project 2010 Feature Rally: Sync to SharePoint

Sync to SharePoint is a useful feature for those organizations that have SharePoint 2010, but not Project Server 2010 — or for those that have both, but prefer to use […]

2 min read
•over 16 years ago•Updated 10 months ago•
D
Daniel BellAuthor
Project Management
Microsoft Project
Best Practices
Productivity
D
Daniel Bell

Content Writer

Daniel Bell, PMP, MCT, MCP, MCTS, is the founder and CEO of MS Project Now!, a consultancy focused on delivering project, portfolio, and business management solutions. Dan has already completed several upgrade projects to the Project Server 2010 beta. He has a strong background in enterprise project and portfolio management (EPM). He has worked with the Microsoft Project Portfolio Server application since it was first acquired from UMT by Microsoft and has some of the most complex portfolio server implementation experience in the United States. In addition Dan has extensive experience with database maintenance and design, systems architecture planning, networking technologies, and server operating systems, as well as experience building servers from the ground up. Dan enjoys balancing his work commitments with skiing, exercise, playing the guitar, and coaching members of youth sport.

View all articles by Daniel Bell
Related Content

Continue Reading

Discover more insights and articles that complement your current reading

Collaboration challenges in remote projects (and how to fix each one)
Articles
1 min read

Collaboration challenges in remote projects (and how to fix each one)

Discover 5 common remote project collaboration challenges, from knowledge silos to unclear ownership, and learn practical ways to keep teams aligned and work moving.

A
Anonymous
9 days ago
Read
An Introduction to the PMI Practice Standard for Scheduling Conformance Index
Articles
1 min read

An Introduction to the PMI Practice Standard for Scheduling Conformance Index

Learn how the Conformance Index in PMI’s Practice Standard for Scheduling scores a CPM schedule model, and how to assess its components in any scheduling tool.

A
Anonymous
20 days ago
Read
A PM’s Halloween Survival Guide: The Sequel You Didn’t Want but Definitely Need
Articles
1 min read

A PM’s Halloween Survival Guide: The Sequel You Didn’t Want but Definitely Need

Part II of the PM Halloween survival guide takes on shape-shifting requirements and dependencies that won’t stay resolved, with practical defenses for each.

A
Anonymous
about 1 month ago
Read
Explore All Articles