I recently learned something new about Microsoft Project. This new knowledge is an extension of how Project calculates the Cost value for each task. As most of us already know, the software calculates the Cost value for each task as the sum of the Cost values for each resource assigned to the task. For example, in the following figure notice that Cost value for the Define Work Breakdown structure ($9,600) is simply the total of the Cost values for the three resources assigned to this task ($3,200 for each of the three resources). This is the behavior that we expect to see in Microsoft Project.

Last week one of our clients ran into an interesting situation with the task Cost field when they discovered that one of their project managers had manually typed the Cost value for a task. What the client saw in the project is similar to the project shown in the figure below. The client had a custom view applied, which in this case was the 02 – Budgeting and Cost Planning view. Notice that this view shows the Budget Cost and Cost columns for each task. Notice also that the Cost value for the Define Work Breakdown Structure task ($25,000) is not the sum of the Cost values for the three assigned resources (it should be $9,600).

As you might surmise, when the client saw this in the project, they were concerned. They reached out to our Delivery team to find out how it is possible for a project manager to manually type a Cost value for an individual task. They questioned whether this was a bug (otherwise known as a “feature”) in the software or something added by design. As a member of our Delivery team, I love “brain teasers” like this, so I gladly accepted the challenge to solve this problem.

The first thing I did was to apply the default Task Usage view and then to apply the default Cost table. With those two simple steps, I could quickly determine what happens when a project manager manually types a task Cost value. In this next figure notice that when I manually typed “$25,000” in the Cost column, Microsoft Project calculated a “Fixed Cost” value of $15,400 for this task.

This situation reminded me that the Total Cost value for any task is the sum of the Total Cost values for each resource assigned to the task, plus any Fixed Cost amount associated with the task. When I manually typed the $25,000 value in the Total Cost column for the task, Project assumed that there is an additional cost for this task, and the software entered this additional cost in the Fixed Cost column! The $15,400 value in the Fixed Cost column is the difference between the value I manually entered in the Total Cost column ($25,000) and the calculated total of the Total Cost values for the three resources assigned ($9,600).

So, I think you would agree that this behavior is definitely not a bug and is certainly by design. Keep in mind that there’s no way to prevent a project manager from manually typing a task Cost value, so keep your eyes on the Fixed Cost column for any projects you audit.

Do you have your own tricks for staying on top of manually entered data? Share them with the MPUG community in the comments below.

A version of this article originally appeared on the Sensei Project Solutions blog here.

Get Weekly PM Insights

Join 500,000+ PMs receiving updates on the latest PM methodologies, PDU opportunities, tool reviews, career tips, and member exclusives.

PMI ATP
PMI Authorized Training Partner
REP #4082

Learning Paths

PMP® TrainingCAPM® TrainingPgMP® TrainingPMI-ACP® TrainingMS ProjectMS PlannerMS TeamsJira

PM Resources

PDU TrackerLive WebinarsSalary CalculatorTool ComparisonsJob BoardKnowledge BasePM Glossary

Community

Discussion ForumStudy GroupsEvents Calendar

Follow Us

LinkedInYouTubeTwitterFacebook
MPUG Logo

© 2025 MPUG. All rights reserved.

TermsPrivacySitemap
Articles

Manually Entering Task Costs — How Is This Even Possible?

I recently learned something new about Microsoft Project. This new knowledge is an extension of how Project calculates the Cost value for each task. As most of us already know, […]

3 min read
•over 8 years ago••
D
Dale HowardAuthor
Project Management
Microsoft Project
Best Practices
Productivity
D
Dale Howard

Content Writer

Dale Howard is currently a Senior PPM Consultant with Arch Systems, Inc. His hair and beard have turned white because of using Microsoft's project management tools for more than 20 years. Dale started his career using Microsoft Project 4.0 for Windows 95 and began using Microsoft's PPM tools when they introduced Project Central in 2000. Dale is the co-author of 23 books in Microsoft Project, Project Server, and Project Online. He is currently one 0f 26 Microsoft Project MVPs in the entire world and one of only 4 Project MVPs in the United states.

View all articles by Dale Howard
Related Content

Continue Reading

Discover more insights and articles that complement your current reading

Two Project Manager Agent Features You Might Like
Articles
5 min read

Two Project Manager Agent Features You Might Like

Discover two game-changing features of Microsoft’s Project Manager Agent including agent-to-agent communication and the new integrated interface in Planner.

E
Erik van Hurck
about 1 month ago
Read
Master Dependency Analysis in Microsoft Project with SSI Tools!
Articles
2 min read

Master Dependency Analysis in Microsoft Project with SSI Tools!

Learn how to master dependency analysis in Microsoft Project using SSI Tools’ Directional Path, Connecting Path, and Dependency Tracer to analyze predecessors, successors, and project logic.

K
Kenny Arnold
about 1 month ago
Read
A PM’s Halloween Survival Guide
Articles
5 min read

A PM’s Halloween Survival Guide

Discover the spooky parallels between Halloween and project management, from scope creep monsters to ghosted team members, in this fun survival guide for PMs.

R
Ronald B. Smith, MBA, PMP
about 2 months ago
Read
Explore All Articles