Back to ArticlesBack

Join 50,000+ PM Professionals

Get expert PM insights, PMP prep tips, and earn PDUs with exclusive content delivered weekly.

MPUG - Master Project User GroupMPUG - Master Project User Group

Communication on a lengthy, complex project isn’t a simple matter. Multi-year initiatives can require thousands of lines of detail in a project plan. Summarizing those details in an understandable way can vex even the most versatile project manager. Yet, a huge global defense contractor faced just that challenge. As an incentive requirement of a customer contract for building large engines, the defense company needed to come up with a way to make a roadmap that would fit on a single page and still be readable.

The vision was to communicate to the project stakeholders the program status, to enable them to execute decisions based on accurate, timely information. But the customer had found that without a one-page chart, people had trouble visualizing key assumptions. They couldn’t get their heads around how changes to various milestone events would affect the final delivery schedule, particularly when the project had multiple milestones being worked on by different teams.

Also, there were disconnects between project management tools. The integrated master schedule and program milestone charts being generated for team and customer meetings displayed data that didn’t always synch up. Charts had variations in formatting, information, and data display. Plus, they were being created manually, which meant that each time the schedule was updated, the charts had to be recreated manually too.

The defense company presented the customer with six different one-page samples, generated using Microsoft’s Visio, Excel, and PowerPoint. But, recalls Marilyn Buckelew, a planning analyst for the contractor, all of the samples were rejected. “The size of the print was too small. They couldn’t get five years’ worth of information into Excel or PowerPoint. The customer kept saying, ‘We can’t tell what’s going on. We can’t read it.'”

Buckelew happened to overhear somebody from one of the teams expressing concern about yet another deadline approaching on the project without a definitive solution to the requirement of the one-page report, and she spoke up. Buckelew had been using a product called Milestones Professional from KIDASA Software for other work, and she thought it would meet the requirements forthis project as well.

The primary purpose of Milestones is to generate a “bird’s eye view” of a project visually. As Buckelew explains, “You can choose the fields in Microsoft Project to pull out and display in a report giving the customer a high level visual of the project on one page.”

She worked with people at both her company and the customer to develop the reports that each team would eventually produce. “It was an iterative process as the people determined the appropriate level forthe data: ‘Are these the milestones you want to see?'” she says.


How A User Taps Milestones Professional

Marilyn Buckelew uses KIDASA Software’s Milestones Professional in multiple ways:

  • To create freeform master phase schedules by manually tagging the symbols.
  • To mark events such as reviews, in the master schedule using a flag field and then run a quick report, using Milestones Professional templates.
  • To create a top-level roadmap from multiple programs, using a refresh feature. She says this is especially useful for executive project planning.
  • To do “what-if” scenarios that show the impact of proposed changes to the master schedule through a baseline change request.
  • To do monthly reporting after status updates.
  • To share schedules with customers who don’t use Microsoft Project by creating a PDF or PPT files.

Now each of four teams uses Milestones monthly to generate a top-level chart created from data taken directly out of Microsoft Project plans. These are delivered to stakeholders, used in customer and team meetings, and posted to a bulletin board in the project team’s hallway, where they can be viewed and validated as people pass by.

Focus: Getting Your Project People on the Same Page

“The visual nature of the reports really helps,” she notes. “It helps people see that big picture of how things fit together. Each team is focused on what they’re doing. It’s hard to see what the different handoffs are between the teams. These reports are a great communication starter to get people to talk with each other about collaborating on dates and handoffs, especially when there are baseline change requests.”

Eventually, the Milestones reporting project became a Six Sigma project, which showed that the shift from the manual chart creation to an automated approach that could be done in minutes removed $100,000 in project costs each year. The company for whom Buckelew works was able to claim the incentive reward stipulated in the contract, and,she adds,”increased customer satisfaction.”

“This tool and resource provides collaborative opportunities which make a huge difference not only in my work, but in the work done by the whole team,” Buckelew says. “It helps us get on the same page. It helps us see that one view. I’ve become a huge fan of Milestones Professional.”

Get Weekly PM Insights

Join 50,000+ PMs receiving updates on the latest PM methodologies, PDU opportunities, tool reviews, career tips, and member exclusives.

PMI ATP
PMI Authorized Training Partner
REP #4082

Learning Paths

PMP® TrainingCAPM® TrainingPgMP® TrainingPMI-ACP® TrainingMS ProjectMS PlannerMS TeamsJira

PM Resources

PDU TrackerLive WebinarsSalary CalculatorTool ComparisonsJob BoardKnowledge BasePM Glossary

Community

Discussion ForumStudy GroupsEvents Calendar

Follow Us

LinkedInYouTubeTwitterFacebook
MPUG Logo

© 2026 MPUG. All rights reserved.

TermsPrivacySitemap
Articles

Focus: Getting Your Project People on the Same Page

Communication on a lengthy, complex project isn’t a simple matter. Multi-year initiatives can require thousands of lines of detail in a project plan. Summarizing those details in an understandable way […]

4 min read
•about 15 years ago•Updated 20 days ago•
D
Dian SchaffhauserAuthor
Project Management
Microsoft Project
Best Practices
Productivity
D
Dian Schaffhauser

Content Writer

Dian Schaffhauser is MPUG's editor. She's been covering project management, business transformation and topics technical as a journalist and editor since IBM released its first PC. She invites you to send your best story ideas for MPUG to her at editor@mpug.com. She promises to let you know what she really thinks.

View all articles by Dian Schaffhauser
Related Content

Continue Reading

Discover more insights and articles that complement your current reading

How Reserves Keep Projects Alive
Articles
4 min read

How Reserves Keep Projects Alive

Learn how project reserves protect your budget and schedule from unexpected risks, including when and how to use contingency, management, schedule, and cost reserves effectively.

R
Ronald B. Smith, MBA, PMP
17 days ago
Read
Why Platform Migrations Fail (And How to Land Yours Successfully)
Articles
4 min read

Why Platform Migrations Fail (And How to Land Yours Successfully)

Learn why platform migrations fail and how to land yours successfully using proven change management tactics for PMOs facing tool transitions like Project Online’s retirement.

T
The MPUG Community
20 days ago
Read
Beyond Project Online: Why Now Is the Time to Plan Your Move to Modern Portfolio Management and How We Can Help
Articles
5 min read

Beyond Project Online: Why Now Is the Time to Plan Your Move to Modern Portfolio Management and How We Can Help

Microsoft Project Online retires September 2026. Learn why now is the time to plan your transition to modern portfolio management and join our free webinar on January 28.

T
The MPUG Community
about 1 month ago
Explore All Articles
Read