In the active project plan file, apply the proper command sequence to open the File Properties dialog box. In Project 2013, that’s File > Info > Project Information > Advanced Properties.

1. On the Custom tab, enter a name for the information you want to display.
2. Select a Type and select the checkbox Link to content. The Source box will display the project summary task fields that can be linked to the custom information specified in the Name box.
3. Click Add to include the custom information defined to the Properties box.
4. Click OK to close the dialog box and exit Project by closing the file.

In order to test this, locate the file on the computer and right-click its desktop shortcut or filename in the folder to open the File Properties dialog box. The Custom tab will show the information that has just been added, even in a system with no Microsoft Project installation!

If you want to display your task count without opening your project file, follow these steps.

1. Do the steps above to add the Contact field (Name: TASK COUNT, Type: Text, Source: Contact) to the Custom tab of the File Properties dialog box.
2. In Project, select Use formula to enter this:

iif( [ID] = 0, [Task Count], 0 )

to the task custom number field Number20.
3. Next, open the Project Summary Task, right-click Number20 in the project summary row, select Copy Cell, then right-click Contact cell of the project summary task and apply Paste Special > Paste Link > OK.

Now Contact field will display the task count of the project.

In order to test this, locate the file on the computer and right-click its desktop shortcut or filename in the folder to open the File Properties dialog box. Again, the Custom tab will show the information that has just been added, even in a system with no Microsoft Project installation.

Ismet Kocaman display project info and task count

Get Weekly PM Insights

Join 50,000+ PMs receiving updates on the latest PM methodologies, PDU opportunities, tool reviews, career tips, and member exclusives.

Protected by reCAPTCHA: Privacy & Terms

PMI ATP
PMI Authorized Training Partner
REP #4082

Learning Paths

PMP® TrainingCAPM® TrainingPgMP® TrainingPMI-ACP® TrainingMS ProjectMS PlannerMS TeamsJira

PM Resources

PDU TrackerLive WebinarsSalary CalculatorTool ComparisonsJob BoardKnowledge BasePM Glossary

Community

Discussion ForumStudy GroupsEvents Calendar

Follow Us

LinkedInYouTubeTwitterFacebook
MPUG Logo

© 2026 MPUG. All rights reserved.

TermsPrivacySitemapAdvertise
Articles

Display Project Info and Task Count without Project

In the active project plan file, apply the proper command sequence to open the File Properties dialog box. In Project 2013, that’s File > Info > Project Information > Advanced […]

2 min read
•over 10 years ago•Updated about 2 months ago•
I
Ismet KocamanAuthor
Project Management
Microsoft Project
Best Practices
Productivity
I
Ismet Kocaman

Content Writer

Ismet Kocaman, MCTS, PMP, is a Mechanical Engineer and has more than 15 years of project management experience in the manufacturing sector. He currently provides consultancy to small to mid-sized companies on project management, reorganizing, and streamlining the manufacturing operations. He also conducts training seminars for engineers on MS Project. Contact Ismet at ikocaman.pm@gmail.com.

View all articles by Ismet Kocaman
Related Content

Continue Reading

Discover more insights and articles that complement your current reading

Your Project Online Migration Questions, Answered: Key Takeaways from Ira Brown
Articles
1 min read

Your Project Online Migration Questions, Answered: Key Takeaways from Ira Brown

Ira Brown, president of Project Widgets, breaks down the four realistic migration paths, key deadlines, and a pre-migration inventory checklist to help your organization plan ahead of the September 2026 Project Online retirement.

A
Anonymous
11 days ago
Read
The Compass vs. The Clock: Why Direction Beats Deadlines in Project Management
Articles
1 min read

The Compass vs. The Clock: Why Direction Beats Deadlines in Project Management

Discover why setting clear project direction matters more than chasing deadlines, and how compass-guided leadership delivers real value in project management.

A
Anonymous
22 days ago
Read
The Scripts That Save Projects: What to Say When Everything Goes Wrong
Articles
1 min read

The Scripts That Save Projects: What to Say When Everything Goes Wrong

Learn word-for-word scripts for handling scope creep, missed deadlines, executive pushback, and team performance issues as a project manager.

A
Anonymous
23 days ago
Read
Explore All Articles