In the active project plan file, apply the proper command sequence to open the File Properties dialog box. In Project 2013, that’s File > Info > Project Information > Advanced Properties.

1. On the Custom tab, enter a name for the information you want to display.
2. Select a Type and select the checkbox Link to content. The Source box will display the project summary task fields that can be linked to the custom information specified in the Name box.
3. Click Add to include the custom information defined to the Properties box.
4. Click OK to close the dialog box and exit Project by closing the file.

In order to test this, locate the file on the computer and right-click its desktop shortcut or filename in the folder to open the File Properties dialog box. The Custom tab will show the information that has just been added, even in a system with no Microsoft Project installation!

If you want to display your task count without opening your project file, follow these steps.

1. Do the steps above to add the Contact field (Name: TASK COUNT, Type: Text, Source: Contact) to the Custom tab of the File Properties dialog box.
2. In Project, select Use formula to enter this:

iif( [ID] = 0, [Task Count], 0 )

to the task custom number field Number20.
3. Next, open the Project Summary Task, right-click Number20 in the project summary row, select Copy Cell, then right-click Contact cell of the project summary task and apply Paste Special > Paste Link > OK.

Now Contact field will display the task count of the project.

In order to test this, locate the file on the computer and right-click its desktop shortcut or filename in the folder to open the File Properties dialog box. Again, the Custom tab will show the information that has just been added, even in a system with no Microsoft Project installation.

Ismet Kocaman display project info and task count

Get Weekly PM Insights

Join 50,000+ PMs receiving updates on the latest PM methodologies, PDU opportunities, tool reviews, career tips, and member exclusives.

Protected by reCAPTCHA: Privacy & Terms

PMI ATP
PMI Authorized Training Partner
REP #4082

Learning Paths

PMP® TrainingCAPM® TrainingPgMP® TrainingPMI-ACP® TrainingMS ProjectMS PlannerMS TeamsJira

PM Resources

PDU TrackerLive WebinarsSalary CalculatorTool ComparisonsJob BoardKnowledge BasePM GlossaryOur Faculty

Community

Discussion ForumStudy GroupsEvents Calendar

Follow Us

LinkedInYouTubeTwitterFacebook
MPUGMaster Project User Group

© 2026 MPUG. All rights reserved.

TermsPrivacySitemapAdvertise
Articles

Display Project Info and Task Count without Project

In the active project plan file, apply the proper command sequence to open the File Properties dialog box. In Project 2013, that’s File > Info > Project Information > Advanced […]

2 min read
•about 11 years ago•Updated 10 months ago•
I
Ismet KocamanAuthor
Project Management
Microsoft Project
Best Practices
Productivity
I
Ismet Kocaman

Content Writer

Ismet Kocaman, MCTS, PMP, is a Mechanical Engineer and has more than 15 years of project management experience in the manufacturing sector. He currently provides consultancy to small to mid-sized companies on project management, reorganizing, and streamlining the manufacturing operations. He also conducts training seminars for engineers on MS Project. Contact Ismet at ikocaman.pm@gmail.com.

View all articles by Ismet Kocaman
Related Content

Continue Reading

Discover more insights and articles that complement your current reading

Collaboration challenges in remote projects (and how to fix each one)
Articles
1 min read

Collaboration challenges in remote projects (and how to fix each one)

Discover 5 common remote project collaboration challenges, from knowledge silos to unclear ownership, and learn practical ways to keep teams aligned and work moving.

A
Anonymous
10 days ago
Read
An Introduction to the PMI Practice Standard for Scheduling Conformance Index
Articles
1 min read

An Introduction to the PMI Practice Standard for Scheduling Conformance Index

Learn how the Conformance Index in PMI’s Practice Standard for Scheduling scores a CPM schedule model, and how to assess its components in any scheduling tool.

A
Anonymous
22 days ago
Read
A PM’s Halloween Survival Guide: The Sequel You Didn’t Want but Definitely Need
Articles
1 min read

A PM’s Halloween Survival Guide: The Sequel You Didn’t Want but Definitely Need

Part II of the PM Halloween survival guide takes on shape-shifting requirements and dependencies that won’t stay resolved, with practical defenses for each.

A
Anonymous
about 1 month ago
Read
Explore All Articles