In the active project plan file, apply the proper command sequence to open the File Properties dialog box. In Project 2013, that’s File > Info > Project Information > Advanced Properties.

1. On the Custom tab, enter a name for the information you want to display.
2. Select a Type and select the checkbox Link to content. The Source box will display the project summary task fields that can be linked to the custom information specified in the Name box.
3. Click Add to include the custom information defined to the Properties box.
4. Click OK to close the dialog box and exit Project by closing the file.

In order to test this, locate the file on the computer and right-click its desktop shortcut or filename in the folder to open the File Properties dialog box. The Custom tab will show the information that has just been added, even in a system with no Microsoft Project installation!

If you want to display your task count without opening your project file, follow these steps.

1. Do the steps above to add the Contact field (Name: TASK COUNT, Type: Text, Source: Contact) to the Custom tab of the File Properties dialog box.
2. In Project, select Use formula to enter this:

iif( [ID] = 0, [Task Count], 0 )

to the task custom number field Number20.
3. Next, open the Project Summary Task, right-click Number20 in the project summary row, select Copy Cell, then right-click Contact cell of the project summary task and apply Paste Special > Paste Link > OK.

Now Contact field will display the task count of the project.

In order to test this, locate the file on the computer and right-click its desktop shortcut or filename in the folder to open the File Properties dialog box. Again, the Custom tab will show the information that has just been added, even in a system with no Microsoft Project installation.

Ismet Kocaman display project info and task count

Get Weekly PM Insights

Join 50,000+ PMs receiving updates on the latest PM methodologies, PDU opportunities, tool reviews, career tips, and member exclusives.

Protected by reCAPTCHA: Privacy & Terms

PMI ATP
PMI Authorized Training Partner
REP #4082

Learning Paths

PMP® TrainingCAPM® TrainingPgMP® TrainingPMI-ACP® TrainingMS ProjectMS PlannerMS TeamsJira

PM Resources

PDU TrackerLive WebinarsSalary CalculatorTool ComparisonsJob BoardKnowledge BasePM Glossary

Community

Discussion ForumStudy GroupsEvents Calendar

Follow Us

LinkedInYouTubeTwitterFacebook
MPUG Logo

© 2026 MPUG. All rights reserved.

TermsPrivacySitemapAdvertise
Articles

Display Project Info and Task Count without Project

In the active project plan file, apply the proper command sequence to open the File Properties dialog box. In Project 2013, that’s File > Info > Project Information > Advanced […]

2 min read
•over 10 years ago•Updated 3 months ago•
I
Ismet KocamanAuthor
Project Management
Microsoft Project
Best Practices
Productivity
I
Ismet Kocaman

Content Writer

Ismet Kocaman, MCTS, PMP, is a Mechanical Engineer and has more than 15 years of project management experience in the manufacturing sector. He currently provides consultancy to small to mid-sized companies on project management, reorganizing, and streamlining the manufacturing operations. He also conducts training seminars for engineers on MS Project. Contact Ismet at ikocaman.pm@gmail.com.

View all articles by Ismet Kocaman
Related Content

Continue Reading

Discover more insights and articles that complement your current reading

Are You Running a Risk Meeting or a Risk Workshop?
Articles
1 min read

Are You Running a Risk Meeting or a Risk Workshop?

Learn the difference between a risk meeting and a risk workshop, and why structured risk workshops help project teams identify owners, define actions, and protect project outcomes.

A
Anonymous
3 days ago
Read
“I Need a Dashboard by Friday” – How AI Just Made That Possible
Articles
1 min read

“I Need a Dashboard by Friday” – How AI Just Made That Possible

Need a dashboard by Friday? Discover how AI tools like ChatGPT can help you build an Excel dashboard quickly and easily—no advanced technical skills required. Learn how to turn plain-English requests into real, working reports with spreadsheets that actually work for you.

A
Anonymous
3 days ago
Read
Why Tools Matter More Than Ever in Project Management (And Why Most Organizations Still Get Them Wrong)
Articles
1 min read

Why Tools Matter More Than Ever in Project Management (And Why Most Organizations Still Get Them Wrong)

Most PPM tools fail because they’re built for oversight, not adoption. Here’s how to design for decisions instead, and why Smartsheet bridges the gap.

A
Anonymous
5 days ago
Read
Explore All Articles