Carol from Madison, WI asks: Is there a view where I can see the summary tasks as well as the detail tasks for over-allocated resources? I’d also like to see the resource usage for the resources at the same time.

Answer: I understand your desire to see this information. When schedulers reuse the same task names within a project schedule and resources are over-allocated, it’s hard to determine which of the same named tasks are affected. There’s no standard view to show summary task names along with detail task names, but you can easily create a custom view.

One of the standard views for seeing over-allocated resource information is the Resource Allocation view, shown below. In this example the Testers are over-allocated. Tasks are in a summary task grouping, and you can’t tell which summary group the tasks belong to.The same task name is shown more than once.

Ask the Experts: Reports on Over-allocated Resources

If renaming tasks to indicate which work breakdown structure (WBS) section tasks belong to isn’t an option, then a customized view that has the Gantt chart on the top and the Resource Usage view on the bottom could help solve the problem. Here’s how to create the view.

In Project 2010:

1. Task | Gantt Chart | More Views | New

In earlier versions of Project:

1. View | More Views | New

2. Create a Combination view

3. In the view Definition box:

a. Name: Gantt/Resource Usage.
b. Primary view: Gantt Chart.
c. Details Pane: Resource Usage.
d. Check Show in menu to add the View to the shortcut menu.
e. Click OK to close the box.

Ask the Experts: Reports on Over-allocated Resources

Only one resource may be selected at a time. Rerun the filter for each over-allocated resource. The results are shown below.

In Project 2010:

1. Task | Gantt Chart | Gantt/Resource Usage.
2. To apply the filter: View | Click on the down arrow for filters | select Using Resource.

In earlier versions of Project:

1. View | Gantt/Resource Usage.
2. To apply the filter: Project | Filter for: | Using Resource.

Ask the Experts: Reports on Over-allocated Resources

Once the view is created, consider saving it in the Organizer for future use.

To save an object in the Organizer using Project 2010:

1. File | Info | Organizer
2. Click on the View tab
3. Click on Gantt/Resource Usage on the right
4. Click on Copy to copy it into the Organizer (Global.mpt)

To save an object in the Organizer using earlier versions of Project:

1. Tools | Organizer
2. Click on the View tab
3. Click on Gantt/Resource Usage on the right
4. Click on Copy to copy it into the Organizer (Global.mpt)

Get Weekly PM Insights

Join 50,000+ PMs receiving updates on the latest PM methodologies, PDU opportunities, tool reviews, career tips, and member exclusives.

Protected by reCAPTCHA: Privacy & Terms

PMI ATP
PMI Authorized Training Partner
REP #4082

Learning Paths

PMP® TrainingCAPM® TrainingPgMP® TrainingPMI-ACP® TrainingMS ProjectMS PlannerMS TeamsJira

PM Resources

PDU TrackerLive WebinarsSalary CalculatorTool ComparisonsJob BoardKnowledge BasePM Glossary

Community

Discussion ForumStudy GroupsEvents Calendar

Follow Us

LinkedInYouTubeTwitterFacebook
MPUG Logo

© 2026 MPUG. All rights reserved.

TermsPrivacySitemapAdvertise
Articles

Ask the Experts: Reports on Over-allocated Resources

Carol from Madison, WI asks: Is there a view where I can see the summary tasks as well as the detail tasks for over-allocated resources? I’d also like to see […]

2 min read
•over 15 years ago•Updated about 1 month ago•
E
Ellen LehnertAuthor
Project Management
Microsoft Project
Best Practices
Productivity
E
Ellen Lehnert

Content Writer

Ellen Lehnert, PMP, Microsoft Project MVP, MCP, is a independent consultant and trainer on Microsoft Project and Project Server. She has taught Microsoft Project over 400 times and is the author of  MS Project 2010 and 2013 published courseware. Ellen is also a contributor and tech editor for many reference books, a developer for the Microsoft Project certification tests and is a frequent meeting speaker for Microsoft, MPUG and PMI. Contact Ellen at ellen@lehnertcs.com.

View all articles by Ellen Lehnert
Related Content

Continue Reading

Discover more insights and articles that complement your current reading

The Compass vs. The Clock: Why Direction Beats Deadlines in Project Management
Articles
1 min read

The Compass vs. The Clock: Why Direction Beats Deadlines in Project Management

Discover why setting clear project direction matters more than chasing deadlines, and how compass-guided leadership delivers real value in project management.

A
Anonymous
10 days ago
Read
The Scripts That Save Projects: What to Say When Everything Goes Wrong
Articles
1 min read

The Scripts That Save Projects: What to Say When Everything Goes Wrong

Learn word-for-word scripts for handling scope creep, missed deadlines, executive pushback, and team performance issues as a project manager.

A
Anonymous
12 days ago
Read
How Reserves Keep Projects Alive
Articles
1 min read

How Reserves Keep Projects Alive

Learn how project reserves protect your budget and schedule from unexpected risks, including when and how to use contingency, management, schedule, and cost reserves effectively.

A
Anonymous
about 1 month ago
Read
Explore All Articles