Claire asks: When looking at a resource usage sheet displaying assigned work, how does one distinguish between unallocated time and exception time? If, for example, the week of 10/19 for a particular engineer is blank because that engineer is on vacation (as opposed to unassigned to any projects during that week,), can this exception be displayed in the Resource Usage sheet? I know that Project will schedule around this exception, but it would be handy to have the exception visible for the Engineering Manager to see.

Answer: The information you need can be displayed, but it will be called “Remaining Availability.” Let’s look at the example below. The resource is booked to work Monday through Friday on a task.

Figure 1. The resource is scheduled to work M-F.

Ask the Experts: Displaying Availability Exceptions in Resource Usage Sheet

In the next step we go into the resource’s availability calendar and block out availability for Wednesday and Thursday. Note the result of the assignment. Claire’s question is in regard to the fact that you can’t see why the assignment looks like it does.

Figure 2. Here, we designate exception time.

Ask the Experts: Displaying Availability Exceptions in Resource Usage Sheet

The solution to this would be if you could find out more information about the resource availability. If you right click on the right side of the screen, a menu comes up; You’ll be able to click on “Remaining Availability” as a column of information to be added to this view. Another way of getting the menu is through Format | Details | Remaining Availability. If you choose the option “Detail Styles,” you’ll have the ability to add many more columns of information. In this way, you could create views for different functions: planning, tracking, reporting, etc. See the result of adding remaining availability to the view:

Figure 3. Here we add Remaining availability to the columns of information.

Ask the Experts: Displaying Availability Exceptions in Resource Usage Sheet

Adding this information will allow you to see that no work was assigned because there was no availability on those days. If you need more information, you might consider obtaining a Gantt chart for the resource showing his calendar. See the example in Figure 4.

Figure 4. A Gantt chart view of the resource.

Ask the Experts: Displaying Availability Exceptions in Resource Usage Sheet

To obtain the view shown in Figure 4, I applied the “Using resource” filter and selected Cost Engineer to the Gantt chart. I then changed the calendar to be shown on the Gantt chart from Standard to Cost Engineer by going to Format | Timescale | Non-working time and selecting Cost Engineer for the calendar. All resources calendars may be shown this way; just remember to restore the project calendar to the view later or create a separate custom view. Another idea might be to use the Calendar view and show just the resource and his or her calendar. These options, however, will only show non-working days, not partial time off. Details about partial time available would best be seen in the Resource Usage view.

Get Weekly PM Insights

Join 500,000+ PMs receiving updates on the latest PM methodologies, PDU opportunities, tool reviews, career tips, and member exclusives.

PMI ATP
PMI Authorized Training Partner
REP #4082

Learning Paths

PMP® TrainingCAPM® TrainingPgMP® TrainingPMI-ACP® TrainingMS ProjectMS PlannerMS TeamsJira

PM Resources

PDU TrackerLive WebinarsSalary CalculatorTool ComparisonsJob BoardKnowledge BasePM Glossary

Community

Discussion ForumStudy GroupsEvents Calendar

Follow Us

LinkedInYouTubeTwitterFacebook
MPUG Logo

© 2025 MPUG. All rights reserved.

TermsPrivacySitemap
Articles

Ask the Experts: Displaying Availability Exceptions in Resource Usage Sheet

Claire asks: When looking at a resource usage sheet displaying assigned work, how does one distinguish between unallocated time and exception time? If, for example, the week of 10/19 for […]

3 min read
•about 17 years ago••
E
Ellen LehnertAuthor
Project Management
Microsoft Project
Best Practices
Productivity
E
Ellen Lehnert

Content Writer

Ellen Lehnert, PMP, Microsoft Project MVP, MCP, is a independent consultant and trainer on Microsoft Project and Project Server. She has taught Microsoft Project over 400 times and is the author of  MS Project 2010 and 2013 published courseware. Ellen is also a contributor and tech editor for many reference books, a developer for the Microsoft Project certification tests and is a frequent meeting speaker for Microsoft, MPUG and PMI. Contact Ellen at ellen@lehnertcs.com.

View all articles by Ellen Lehnert
Related Content

Continue Reading

Discover more insights and articles that complement your current reading

Two Project Manager Agent Features You Might Like
Articles
5 min read

Two Project Manager Agent Features You Might Like

Discover two game-changing features of Microsoft’s Project Manager Agent including agent-to-agent communication and the new integrated interface in Planner.

E
Erik van Hurck
about 1 month ago
Read
Master Dependency Analysis in Microsoft Project with SSI Tools!
Articles
2 min read

Master Dependency Analysis in Microsoft Project with SSI Tools!

Learn how to master dependency analysis in Microsoft Project using SSI Tools’ Directional Path, Connecting Path, and Dependency Tracer to analyze predecessors, successors, and project logic.

K
Kenny Arnold
about 2 months ago
Read
A PM’s Halloween Survival Guide
Articles
5 min read

A PM’s Halloween Survival Guide

Discover the spooky parallels between Halloween and project management, from scope creep monsters to ghosted team members, in this fun survival guide for PMs.

R
Ronald B. Smith, MBA, PMP
2 months ago
Read
Explore All Articles