Back to ArticlesBack

Subscribe to our newsletter

Get the latest articles and resources sent straight to your inbox.

MPUG

A reader writes: My boss has said the project must be finished by 8 July. I’ve tried scheduling from the end date, but is there a better way?

Answer: Probably! Scheduling from the end date can be set via Project | Project Information | Schedule from: | Project Finish Date. Note the words underneath: All tasks begin as late as possible.” Therein lies the rub — every task is now critical and the project has lost all its flexibility and is likely to be doomed to failure!

Figure 1: Scheduling from the end date.

Ask the Expert: When Scheduling, Start at the Beginning

Much better to schedule from the start, and if you select Project Start Date, then “All tasks begin as soon as possible.” This will give you the maximum flexibility, provided you haven’t entered any task start or finish dates (which sets constraints) or entered any other constraints. The temptation is to enter dates rather than let Project do what it’s best at — calculating a workable schedule for you. The strongest constraints, Must Start On and Must Finish On, lead us to believe that that is what will happen. Just because you enter a Must Finish On constraint doesn’t mean that it will happen that way. No — don’t use such constraints. Much better to enter the Deadline Date.

Figure 2: Using Project’s Deadline Date field.

Ask the Expert: When Scheduling, Start at the Beginning

Double-click on your Finish milestone (create one if you haven’t already done so). In the Task Information dialog select a deadline date (click the drop-down arrow to see a calendar) for this example 9 Jul 09 and OK.

Figure 3: Designating the deadline date.

Ask the Expert: When Scheduling, Start at the Beginning

The finish milestone now had an arrow positioned at 9 Jul 09. So, as it stands, we should be OK as the scheduled end date is three working days before the deadline.
However, let’s suppose as our project progresses, we get stuck on one task causing a five-day delay. Having entered the delay, the effect on our finish date is made obvious to us as the Deadline doesn’t move; but the milestone has now overtaken the deadline. As this means that we can’t make our deadline, Project also adds an indicator — hover your mouse over the indicator to read the detail.

Figure 4: The Project indicator for missed deadlines.

Ask the Expert: When Scheduling, Start at the Beginning

We can now start earning our pay by examining the detail and make decisions on how to recoup the lateness and bring it back into time. This can be done in one or all of three options: 1) reducing the Durations of subsequent tasks by increasing resources; 2) working overtime; or 3) reducing the amount of Work required. This isn’t to say you can’t come to the same conclusions by scheduling from the Finish or setting a Must Finish On constraint — but at least you can see the effect and size of the delay, allowing you to more easily make considered adjustments to finish on time. Good luck!

For more on this topic, you might like to have a look at Mike’s article on manipulating tasks, including deadline dates. Also check this “Certification Insider” column by Bonnie Biafore.

Get Weekly PM Insights

Join 500,000+ PMs receiving updates on the latest PM methodologies, PDU opportunities, tool reviews, career tips, and member exclusives.

PMI ATP
PMI Authorized Training Partner
REP #4082

Learning Paths

PMP® TrainingCAPM® TrainingPgMP® TrainingPMI-ACP® TrainingMS ProjectMS PlannerMS TeamsJira

PM Resources

PDU TrackerLive WebinarsSalary CalculatorTool ComparisonsJob BoardKnowledge BasePM Glossary

Community

Discussion ForumStudy GroupsEvents Calendar

Follow Us

LinkedInYouTubeTwitterFacebook
MPUG Logo

© 2025 MPUG. All rights reserved.

TermsPrivacySitemap
Articles

Ask the Expert: When Scheduling, Start at the Beginning

A reader writes: My boss has said the project must be finished by 8 July. I’ve tried scheduling from the end date, but is there a better way? Answer: Probably! […]

3 min read
•over 16 years ago••
A
Author
Project Management
Microsoft Project
Best Practices
Productivity
A

Content Writer

View all articles by
Related Content

Continue Reading

Discover more insights and articles that complement your current reading

Two Project Manager Agent Features You Might Like
Articles
5 min read

Two Project Manager Agent Features You Might Like

Discover two game-changing features of Microsoft’s Project Manager Agent including agent-to-agent communication and the new integrated interface in Planner.

E
Erik van Hurck
about 1 month ago
Read
Master Dependency Analysis in Microsoft Project with SSI Tools!
Articles
2 min read

Master Dependency Analysis in Microsoft Project with SSI Tools!

Learn how to master dependency analysis in Microsoft Project using SSI Tools’ Directional Path, Connecting Path, and Dependency Tracer to analyze predecessors, successors, and project logic.

K
Kenny Arnold
about 1 month ago
Read
A PM’s Halloween Survival Guide
Articles
5 min read

A PM’s Halloween Survival Guide

Discover the spooky parallels between Halloween and project management, from scope creep monsters to ghosted team members, in this fun survival guide for PMs.

R
Ronald B. Smith, MBA, PMP
about 2 months ago
Read
Explore All Articles