Back to ArticlesBack

Join 50,000+ PM Professionals

Get expert PM insights, PMP prep tips, and earn PDUs with exclusive content delivered weekly.

MPUG - Master Project User GroupMPUG - Master Project User Group

Jay of Mt. Vernon, IL asks: I have tasks that will consume material resources at a rate of a number of items per hour. Is there anyway I can use Microsoft Project to have this calculation performed for me?

Answer: Yes, Project can do this for you, but there are the a few things you should be aware of regarding this capability. This feature will work in Project versions 2000 through 2007, Standard and Professional. Prior to 2000, material resources weren’t an option of the system. To have this feature work, set up a material resource (View | Resource Sheet). Let’s use the example of the work of a painting contractor.

Figure 1. The supplies used by a painting contractor.

Ask the Expert: Accounting for Material Resources

The contractor will require paint, brushes, and paint masks to complete the tasks. Paint will be used at a rate of one gallon per hour; brushes will be three per week; and paint masks will be two per day. The resource is assigned to the task normally.

Figure 2. Assigning the resource to the project.

Ask the Expert: Accounting for Material Resources

In this example, the resource will need 160 hours to complete the task. Next, assign the material resources to the task. Note that the units column indicates the consumption time.

Figure 3. Assigning the material resources to the project.

Ask the Expert: Accounting for Material Resources

In the work column you’ll see that there are 160 hours of work for the task and 160 gallons of paint required, as well as 40 paint masks and 12 paint brushes. The cost will also reflect this estimate.

What I feel you should be aware of is that if the length of your tasks increases, all of the materials resource estimates will also increase. Depending on your application, this could work against you or for you. My suggestion is that if the length of the task changes, make sure the materials values are giving you the desired results.

In the view in Figure 4 I’ve increased the task from four weeks of duration to six weeks. Note the difference in the materials estimates.

Figure 4. A change in task duration drives a change in materials estimates.

Ask the Expert: Accounting for Material Resources

If the tasks are fixed duration, this shouldn’t be an issue as long as the length doesn’t change; but you will find this occurring for fixed work tasks and fixed unit tasks. My concern is that sometimes the time of the task increases during tracking, but you may not need to increase these types of consumables for the tasks. If you want the values to stay constant, simply ignore the recalculation of the materials values in the current work fields and use the baseline work values as the amount of material you’ll need to accomplish the task.

Get Weekly PM Insights

Join 50,000+ PMs receiving updates on the latest PM methodologies, PDU opportunities, tool reviews, career tips, and member exclusives.

PMI ATP
PMI Authorized Training Partner
REP #4082

Learning Paths

PMP® TrainingCAPM® TrainingPgMP® TrainingPMI-ACP® TrainingMS ProjectMS PlannerMS TeamsJira

PM Resources

PDU TrackerLive WebinarsSalary CalculatorTool ComparisonsJob BoardKnowledge BasePM Glossary

Community

Discussion ForumStudy GroupsEvents Calendar

Follow Us

LinkedInYouTubeTwitterFacebook
MPUG Logo

© 2026 MPUG. All rights reserved.

TermsPrivacySitemap
Articles

Ask the Expert: Accounting for Material Resources

Jay of Mt. Vernon, IL asks: I have tasks that will consume material resources at a rate of a number of items per hour. Is there anyway I can use […]

2 min read
•over 17 years ago•Updated 24 days ago•
E
Ellen LehnertAuthor
Project Management
Microsoft Project
Best Practices
Productivity
E
Ellen Lehnert

Content Writer

Ellen Lehnert, PMP, Microsoft Project MVP, MCP, is a independent consultant and trainer on Microsoft Project and Project Server. She has taught Microsoft Project over 400 times and is the author of  MS Project 2010 and 2013 published courseware. Ellen is also a contributor and tech editor for many reference books, a developer for the Microsoft Project certification tests and is a frequent meeting speaker for Microsoft, MPUG and PMI. Contact Ellen at ellen@lehnertcs.com.

View all articles by Ellen Lehnert
Related Content

Continue Reading

Discover more insights and articles that complement your current reading

How Reserves Keep Projects Alive
Articles
1 min read

How Reserves Keep Projects Alive

Learn how project reserves protect your budget and schedule from unexpected risks, including when and how to use contingency, management, schedule, and cost reserves effectively.

A
Anonymous
21 days ago
Read
Why Platform Migrations Fail (And How to Land Yours Successfully)
Articles
1 min read

Why Platform Migrations Fail (And How to Land Yours Successfully)

Learn why platform migrations fail and how to land yours successfully using proven change management tactics for PMOs facing tool transitions like Project Online’s retirement.

A
Anonymous
23 days ago
Read
Beyond Project Online: Why Now Is the Time to Plan Your Move to Modern Portfolio Management and How We Can Help
Articles
1 min read

Beyond Project Online: Why Now Is the Time to Plan Your Move to Modern Portfolio Management and How We Can Help

Microsoft Project Online retires September 2026. Learn why now is the time to plan your transition to modern portfolio management and join our free webinar on January 28.

A
Anonymous
about 1 month ago
Read
Explore All Articles