Background Information

Several months back, a user posted an interesting question in my company’s Microsoft Project user forum. The user was managing a project in which there were tasks that needed to be scheduled to occur on the first working day of each month. He indicated that he knew he could use a Start No Earlier Than (SNET) constraint on each task for this purpose, but he wanted the scheduling of these tasks to be automatic. This means that if the schedule slipped on a predecessor task, he needed these particular “first of the month” tasks to automatically be rescheduled to the first working day of the next month.

So, if the user cannot use constraints, is it still possible to schedule tasks to automatically start on the first working day of the month? Thankfully, the answer is yes.

The Solution

The first part of the solution for this unique scheduling problem requires the project manager to create a custom calendar that shows only the first working day of each month as working time, with all other days in the month shown as nonworking time. To create this calendar, complete the following steps:

1. Click the Project tab to display the Project

2. In the Properties section of the Project ribbon, click the Change Working Time button. Notice in the Change Working Time dialog shown in Figure 1 that the Standard calendar includes company holidays through the year 2022.

Figure 1: Standard calendar with company holidays

3. In the upper-right corner of the Change Working Time dialog, click the Create New Calendar

4. In the Create New Base Calendar dialog, enter a name for the new calendar in the Name field, and then select the Create new base calendar option, as shown in Figure 2.

Figure 2: Create New Base Calendar dialog

5. In the Create New Base Calendar dialog, click the OK button to create the custom calendar.

6. In the calendar grid at the top of the Change Working Time dialog, scroll to the starting month of the project, such as October 2018, for example.

7. In the calendar grid, select every day except for the first working day of the month. For example, notice in Figure 3 how I have selected every day except for Monday, October 1, 2018.

Figure 3: Nonworking days in October selected

8. On the first line of the Exceptions data grid, enter a name for the nonworking time and then press the Right-Arrow key on your computer keyboard to create the nonworking time period. Notice in Figure 4 how I entered the name October 2018 Nonworking Time for this time period.

Figure 4: October 2018 nonworking time instance completed

9. Scroll the calendar grid to the next month.

10. Repeat steps #7-9 to add nonworking time to every month during the life of the project. For best results, add nonworking time instances for a couple of months past the anticipated Finish date of the project. Notice in Figure 5 that I added nonworking time instances for each month from October 2018 through June 2019, even though the project is anticipated to finish in April 2019.

Figure 5: Nonworking time instances completed

11. Click the OK button to close the Change Working Time

The second part of the solution for this unique scheduling problem requires the project manager to assign the custom calendar as a Task Calendar to any task on which the work must be scheduled to start automatically on the first working day of any month. For example, in the project shown in Figure 6, notice that the Monthly Project Review task is currently scheduled to start on Monday, October 29, based on its Finish-to-Start dependency with the Work Package task. According to the original question in the Microsoft Project user forum, this task needs to be automatically scheduled on the first working day of the next month.

Figure 6: Sample project

To assign the calendar as a Task Calendar, complete the following additional steps:

1. Double-click a task that needs to be scheduled on the first working day of the next month.

2. In the Task Information dialog, click the Advanced tab as shown in Figure 7.

Figure 7: Task Information dialog – Advanced page

3. On the Advanced page of the Task Information dialog, click the Calendar pick list and select the custom calendar you created in the previous set of steps, as shown in Figure 8.

Figure 8: Task Information dialog – select a Calendar value

4. On the Advanced page of the Task Information dialog, select the Scheduling ignores resource calendars option, as shown in Figure 9. Selecting this option, by the way, guarantees that the work on this task will always be scheduled to start on the first working day of the next month, no matter which resources are assigned to the task.

Figure 9: Select the Scheduling ignores resource calendars option

5. Click the OK button to apply the custom calendar to the selected task as a Task Calendar. Microsoft Project will automatically reschedule the selected task to start on the first working day of the next month.

For example, notice in Figure 10 how the software correctly scheduled the Monthly Project Review task to start on November 1, the first working day of the next month. If the Finish date of the Work Package task slips past November 1, the Monthly Project Review task will be automatically rescheduled to start on Monday, December 3, the first working day of December.

Figure 10: Monthly Project Review task correctly scheduled

Get Weekly PM Insights

Join 500,000+ PMs receiving updates on the latest PM methodologies, PDU opportunities, tool reviews, career tips, and member exclusives.

PMI ATP
PMI Authorized Training Partner
REP #4082

Learning Paths

PMP® TrainingCAPM® TrainingPgMP® TrainingPMI-ACP® TrainingMS ProjectMS PlannerMS TeamsJira

PM Resources

PDU TrackerLive WebinarsSalary CalculatorTool ComparisonsJob BoardKnowledge BasePM Glossary

Community

Discussion ForumStudy GroupsEvents Calendar

Follow Us

LinkedInYouTubeTwitterFacebook
MPUG Logo

© 2025 MPUG. All rights reserved.

TermsPrivacySitemap
Articles

Schedule Tasks to Occur on the First Working Day of Each Month

Background Information Several months back, a user posted an interesting question in my company’s Microsoft Project user forum. The user was managing a project in which there were tasks that […]

5 min read
•about 7 years ago••
D
Dale HowardAuthor
Project Management
Microsoft Project
Best Practices
Productivity
D
Dale Howard

Content Writer

Dale Howard is currently a Senior PPM Consultant with Arch Systems, Inc. His hair and beard have turned white because of using Microsoft's project management tools for more than 20 years. Dale started his career using Microsoft Project 4.0 for Windows 95 and began using Microsoft's PPM tools when they introduced Project Central in 2000. Dale is the co-author of 23 books in Microsoft Project, Project Server, and Project Online. He is currently one 0f 26 Microsoft Project MVPs in the entire world and one of only 4 Project MVPs in the United states.

View all articles by Dale Howard
Related Content

Continue Reading

Discover more insights and articles that complement your current reading

Two Project Manager Agent Features You Might Like
Articles
5 min read

Two Project Manager Agent Features You Might Like

Discover two game-changing features of Microsoft’s Project Manager Agent including agent-to-agent communication and the new integrated interface in Planner.

E
Erik van Hurck
about 1 month ago
Read
Master Dependency Analysis in Microsoft Project with SSI Tools!
Articles
2 min read

Master Dependency Analysis in Microsoft Project with SSI Tools!

Learn how to master dependency analysis in Microsoft Project using SSI Tools’ Directional Path, Connecting Path, and Dependency Tracer to analyze predecessors, successors, and project logic.

K
Kenny Arnold
about 1 month ago
Read
A PM’s Halloween Survival Guide
Articles
5 min read

A PM’s Halloween Survival Guide

Discover the spooky parallels between Halloween and project management, from scope creep monsters to ghosted team members, in this fun survival guide for PMs.

R
Ronald B. Smith, MBA, PMP
2 months ago
Read
Explore All Articles