Dear Elizabeth:

I run a product team that responds to seasonal demands, and our output fluctuates. We have times when we’re very busy and then a couple of weeks where it’s slow. There’s always work to be done, but when demand ebbs, people’s productivity and engagement does as well. How do I keep my team engaged and motivated during these slow periods? – Riding the Productivity Rollercoaster

Dear Riding:

Let me be a little bit controversial here. How much does it matter if your team has a slow period? If demand is down, and that’s affecting their engagement and motivation, unless they are being downright unprofessional, perhaps you could cut them some slack. It’s hard to remain 100 percent motivated every day of every year, and engagement wanes too.

Not having an interesting piece of work to do is naturally a bit demotivating but that doesn’t stop them switching to “motivated mode” as soon as the next big assignment comes in. As long as they aren’t using your resources to print out copies of their resume, then maybe you want to let them off. Think of it as time that they are using to recharge their batteries until the next busy period.

Having said that, I know why you want to keep the team engaged and motivated, so let’s get back to your question. The first thing to look for is whether there is a pattern. Can you predict when the slower times will be? If so, think ahead and start looking for activities to fill the gaps. These activities might not be what you might call true work but you could organize a staff conference, a team building event, or schedule some professional training for the team. It’s also a time for cross-skilling, where team members can teach each other their particular expertise. That way, you’ll have more cover for vacation and sickness, as well as a broader skill base in the team.

It’s hard to give a blanket recommendation for how to motivate people because everyone is motivated by different things. Some may appreciate the ability to take some extra time off in lieu of hours worked during the busy times. Others may find motivation in being asked to step up and take on more responsibility, such as helping to plan the next big push. Tasks that might take longer if someone less experienced did them would be good to schedule in the slow periods too, as a way of building confidence and leadership in the team.

Every month, project management expert, Elizabeth Harrin, fields readers’ questions about the challenges, risks, and rewards of project work on the LiquidPlanner blog. This selection is used with permission.


Related Content

Webinars (watch for free now!):
From Task Manager to People Manager – The Next Generation of Project Managers
Supercharge your Productivity with New Agile, Kanban and Scrum Features and Capabilities in Microsoft Project

Articles:
Common Issues in Project Management #3: Micromanaging the Team
Ten Project Management Truths
Newly Released Agile Capabilities in MS Project


Get Weekly PM Insights

Join 50,000+ PMs receiving updates on the latest PM methodologies, PDU opportunities, tool reviews, career tips, and member exclusives.

Protected by reCAPTCHA: Privacy & Terms

PMI ATP
PMI Authorized Training Partner
REP #4082

Learning Paths

PMP® TrainingCAPM® TrainingPgMP® TrainingPMI-ACP® TrainingMS ProjectMS PlannerMS TeamsJira

PM Resources

PDU TrackerLive WebinarsSalary CalculatorTool ComparisonsJob BoardKnowledge BasePM Glossary

Community

Discussion ForumStudy GroupsEvents Calendar

Follow Us

LinkedInYouTubeTwitterFacebook
MPUG Logo

© 2026 MPUG. All rights reserved.

TermsPrivacySitemapAdvertise
Articles

Riding the Productivity Roller Coaster

Dear Elizabeth: I run a product team that responds to seasonal demands, and our output fluctuates. We have times when we’re very busy and then a couple of weeks where […]

3 min read
•over 8 years ago•Updated 5 months ago•
E
Elizabeth HarrinAuthor
Project Management
Microsoft Project
Best Practices
Productivity
E
Elizabeth Harrin

Content Writer

Elizabeth Harrin has over twenty years’ experience in projects. Elizabeth has led a variety of IT and process improvement projects including ERP and communications developments. She is also experienced in managing business change, having spent eight years working in financial services (including two based in Paris, France). Elizabeth is the author of 7 project management books including Managing Multiple Projects. She is a Fellow of the Association for Project Management and writes the popular blog, Rebel’s Guide to Project Management.

View all articles by Elizabeth Harrin
Related Content

Continue Reading

Discover more insights and articles that complement your current reading

Why the End of Project Online Might Be the Best Thing for Your Team
Articles
1 min read

Why the End of Project Online Might Be the Best Thing for Your Team

Project Online retires September 30, 2026, and Eric and Jeff Christoph make the case that the smartest move is a complete desktop project-controls environment, not a one-for-one swap.

A
Anonymous
5 days ago
Read
The Catch-22 Project: Why Some Projects Fail Before They Ever Begin
Articles
1 min read

The Catch-22 Project: Why Some Projects Fail Before They Ever Begin

Learn to spot a Catch-22 project, where contradictory requirements make progress impossible, and how to reframe the structure so your team can move forward.

A
Anonymous
5 days ago
Read
Maintaining the Human Element of Leadership in a Technological World
Articles
1 min read

Maintaining the Human Element of Leadership in a Technological World

Learn how leaders can maintain humanity in technology-driven workplaces through emotional intelligence, role clarity, psychological safety, and meaningful recognition.

A
Anonymous
about 1 month ago
Read
Explore All Articles