I recently taught a Microsoft Project 2013 Advanced class to a wonderful group of students. During the class, I suddenly realized how many times I had asked my students to right-click on something in the software to access a shortcut menu. Often times, the fastest way to perform a procedure is to right-click and select an item on a shortcut menu. Allow me to share with you a few of my favorite right-clicking tricks for Microsoft Project 2010 and 2013:

  • Right-click on the Select All button. Microsoft Project displays a shortcut menu containing a list of commonly used tables. For example, Figure 1 shows that I am ready to select the Cost item on the shortcut menu to apply the task Cost table.

rightclick_1
Figure 1: Right-click on the Select All button

  • Right-click on any Ribbon tab. Microsoft Project displays a shortcut menu that offers you multiple options for working with both the Ribbon and the Quick Access Toolbar. For example, Figure 2 shows that I am ready to click the Customize the Ribbon item on the shortcut menu so that I can customize the Ribbon.

rightclick_2
Figure 2: Right-click on a Ribbon tab

  • Right-click anywhere in the white part of the Gantt Chart pane. Microsoft Project displays a shortcut menu with several formatting options, along with two options at the bottom of the menu to display a split screen view. For example, Figure 3 shows that I am ready to select the Show Split item on the shortcut menu so that I can display the Task Entry view (a split view with the Gantt Chart view in the top pane and the Task Entry view in the bottom pane). Notice that you can also select the Show Timeline item to display the Gantt with Timeline view as well.

rightclick_3
Figure 3: Right-click in the white part of the Gantt Chart pane

  • After applying the Task Entry view, you can right-click in the Task Form view to change set of details (fields and columns) displayed in the view. Microsoft Project displays a shortcut men with eight sets of details which you can apply to the Task Form. For example, Figure 4 shows that I am ready to select the Schedule item on the shortcut menu so that I can display the Schedule set of details in the Task Form.

rightclick_4
Figure 4: Right-click in the Task Form view

  • After applying a split view, you might want to change the view displayed in either the top pane or the bottom pane. To do this, right-click in the View Bar area on the far left side of the view. For example, Figure 5 shows that I am ready to select the Task Usage item on the shortcut menu to display the Task Usage view instead of the Task Form view in the bottom pane.

rightclick_5 
Figure 5: Right-click in the View Bar

  • Right-click on a task that displays the “burning man” icon (red stick figure) in the Indicators column, indicating that you have one or more overallocated resources assigned to the task. At the top of the shortcut menu, Microsoft Project displays two items with bold formatting that represent two possible solutions you can use to resolve the overallocation. For example, Figure 6 shows that I am ready to select the Schedule to Available Date item on the shortcut menu to delay the task as a method of resolving the resource overallocation.

rightclick_6
Figure 6: Right-click on a task with an overallocated resource assigned

  • Right-click on a selected block of tasks. Microsoft Project displays a shortcut menu with multiple options for working with all of the selected tasks, such as deleting the selected tasks, inserting new tasks, or setting the selected tasks to Inactive status. For example, Figure 7 shows that I am ready to select the Information item on the shortcut menu to display the Multiple Task Information dialog.

rightclick_7
Figure 7: Right-click on a selected block of tasks

A version of this article originally appeared on the Sensei Project Solutions blog.

Get Weekly PM Insights

Join 50,000+ PMs receiving updates on the latest PM methodologies, PDU opportunities, tool reviews, career tips, and member exclusives.

Protected by reCAPTCHA: Privacy & Terms

PMI ATP
PMI Authorized Training Partner
REP #4082

Learning Paths

PMP® TrainingCAPM® TrainingPgMP® TrainingPMI-ACP® TrainingMS ProjectMS PlannerMS TeamsJira

PM Resources

PDU TrackerLive WebinarsSalary CalculatorTool ComparisonsJob BoardKnowledge BasePM GlossaryOur Faculty

Community

Discussion ForumStudy GroupsEvents Calendar

Follow Us

LinkedInYouTubeTwitterFacebook
MPUGMaster Project User Group

© 2026 MPUG. All rights reserved.

TermsPrivacySitemapAdvertise
Articles

The Power of Right-Clicking in Microsoft Project 2013

I recently taught a Microsoft Project 2013 Advanced class to a wonderful group of students. During the class, I suddenly realized how many times I had asked my students to […]

3 min read
•almost 12 years ago•Updated 10 months ago•
D
Dale HowardAuthor
Project Management
Microsoft Project
Best Practices
Productivity
D
Dale Howard

Content Writer

Dale Howard is currently a Senior PPM Consultant with Arch Systems, Inc. His hair and beard have turned white because of using Microsoft's project management tools for more than 20 years. Dale started his career using Microsoft Project 4.0 for Windows 95 and began using Microsoft's PPM tools when they introduced Project Central in 2000. Dale is the co-author of 23 books in Microsoft Project, Project Server, and Project Online. He is currently one 0f 26 Microsoft Project MVPs in the entire world and one of only 4 Project MVPs in the United states.

View all articles by Dale Howard
Related Content

Continue Reading

Discover more insights and articles that complement your current reading

Collaboration challenges in remote projects (and how to fix each one)
Articles
1 min read

Collaboration challenges in remote projects (and how to fix each one)

Discover 5 common remote project collaboration challenges, from knowledge silos to unclear ownership, and learn practical ways to keep teams aligned and work moving.

A
Anonymous
5 days ago
Read
An Introduction to the PMI Practice Standard for Scheduling Conformance Index
Articles
1 min read

An Introduction to the PMI Practice Standard for Scheduling Conformance Index

Learn how the Conformance Index in PMI’s Practice Standard for Scheduling scores a CPM schedule model, and how to assess its components in any scheduling tool.

A
Anonymous
16 days ago
Read
A PM’s Halloween Survival Guide: The Sequel You Didn’t Want but Definitely Need
Articles
1 min read

A PM’s Halloween Survival Guide: The Sequel You Didn’t Want but Definitely Need

Part II of the PM Halloween survival guide takes on shape-shifting requirements and dependencies that won’t stay resolved, with practical defenses for each.

A
Anonymous
about 1 month ago
Read
Explore All Articles