Back to ArticlesBack

Subscribe to our newsletter

Get the latest articles and resources sent straight to your inbox.

MPUG

When working within a new project, have you ever noticed those question marks in the Duration column for every task that has the default duration of 1 day? If memory serves me correctly, Microsoft introduced a new feature called Estimated Durations in Microsoft Project 2000. In fact, I distinctly remember how very experienced users of the software complained about this new feature, and often asked me how to get rid of it!

By default, the Estimated Durations feature is enabled in every version of the software, which means that you will see a Duration value of “1 day?” for every new task you add to the schedule. This feature is intended for project managers who estimate Duration values rather than Work values in their projects.

Figure 1: Estimated Durations

If you are a project manager who does estimate Duration values in your project, the Estimated Duration feature will display a question mark on the Duration value for every task until you manually enter a Duration value. After you manually enter the Duration value for a task, the question mark symbol will disappear. This means that if a task has the default Duration value of 1 day, and you want the Duration for that task to be 1 day, you must still manually type the 1 day value into the Duration cell to make the question mark disappear. Notice in the following figure that I have manually typed a Duration value for each task in the PHASE I section of the schedule and that the question marks no longer appear for the PHASE I tasks as a consequence.

Figure 2: Duration estimates entered for Phase I tasks

If you are a project manager who estimates Duration values in your projects, the Estimated Duration feature can be very useful. Before finalizing the project schedule, you should visually scan the Duration column, looking for any task Duration value with a question mark. Manually type a Duration value for every remaining task until all the question marks are completely gone.

If you are a project manager who estimates Duration values in your projects, but you manage large projects with a thousand or more tasks, visually scanning the Duration column for question marks can be a cumbersome process. A better approach would be to use the built-in Tasks with Estimated Durations filter. To use this filter, click the View tab to display the View ribbon. In the Data section of the View ribbon, click the Filter pick list and select the Tasks with Estimated Durations filter. By applying this filter, you can quickly spot any residual tasks with an Estimated Duration. Manually type a Duration value for every remaining task until all the question marks are completely gone and then press the F3 function key to clear the filter.

Figure 3: Tasks with Estimated Durations filter

If you are a project manager who estimates Work values rather than Duration values for tasks in your project schedules, you will probably find the Estimated Durations feature of little value to you. For example, notice in the following figure that I assigned Mickey Cobb to the Design 2 task with a Units value of 100% and a Work estimate of 56 hours. After assigning her to the task, Microsoft Project calculated a Duration value of 7 days, but notice that the question mark still remains in the Duration field. The question marks only disappear when a Duration value is manually entered; they do not disappear when the Duration value is calculated.

Figure 4: Estimated Duration does not disappear

If you are a project manager who estimates Work values rather than Duration values for tasks in your project schedules, you will probably want to disable the Estimated Durations feature in all of your projects. To disable this feature, complete the following steps:

  1. Open a project.
  2. Click the File tab and then click the Options button in the Backstage.
  3. In the Project Options dialog, click the Schedule tab.
  4. In the Scheduling options for this project section of the dialog, deselect the Show that scheduled tasks have estimated durations checkbox.
  5. In the Scheduling options for this project section of the dialog, deselect the New scheduled tasks have estimated durations checkbox as well.
  6. Click the OK button.

Figure 5: Disable the Estimated Durations feature

After completing the preceding steps, the question marks in the Duration column will disappear for every task in the schedule. You will need to repeat the preceding steps for every project schedule you manage. In addition, I recommend you complete the preceding steps for every schedule template you use as well.

Get Weekly PM Insights

Join 500,000+ PMs receiving updates on the latest PM methodologies, PDU opportunities, tool reviews, career tips, and member exclusives.

PMI ATP
PMI Authorized Training Partner
REP #4082

Learning Paths

PMP® TrainingCAPM® TrainingPgMP® TrainingPMI-ACP® TrainingMS ProjectMS PlannerMS TeamsJira

PM Resources

PDU TrackerLive WebinarsSalary CalculatorTool ComparisonsJob BoardKnowledge BasePM Glossary

Community

Discussion ForumStudy GroupsEvents Calendar

Follow Us

LinkedInYouTubeTwitterFacebook
MPUG Logo

© 2025 MPUG. All rights reserved.

TermsPrivacySitemap
Articles

About Those Pesky Question Marks in the Duration Column

When working within a new project, have you ever noticed those question marks in the Duration column for every task that has the default duration of 1 day? If memory […]

4 min read
•over 7 years ago••
D
Dale HowardAuthor
Project Management
Microsoft Project
Best Practices
Productivity
D
Dale Howard

Content Writer

Dale Howard is currently a Senior PPM Consultant with Arch Systems, Inc. His hair and beard have turned white because of using Microsoft's project management tools for more than 20 years. Dale started his career using Microsoft Project 4.0 for Windows 95 and began using Microsoft's PPM tools when they introduced Project Central in 2000. Dale is the co-author of 23 books in Microsoft Project, Project Server, and Project Online. He is currently one 0f 26 Microsoft Project MVPs in the entire world and one of only 4 Project MVPs in the United states.

View all articles by Dale Howard
Related Content

Continue Reading

Discover more insights and articles that complement your current reading

Two Project Manager Agent Features You Might Like
Articles
5 min read

Two Project Manager Agent Features You Might Like

Discover two game-changing features of Microsoft’s Project Manager Agent including agent-to-agent communication and the new integrated interface in Planner.

E
Erik van Hurck
about 1 month ago
Read
Master Dependency Analysis in Microsoft Project with SSI Tools!
Articles
2 min read

Master Dependency Analysis in Microsoft Project with SSI Tools!

Learn how to master dependency analysis in Microsoft Project using SSI Tools’ Directional Path, Connecting Path, and Dependency Tracer to analyze predecessors, successors, and project logic.

K
Kenny Arnold
about 1 month ago
Read
A PM’s Halloween Survival Guide
Articles
5 min read

A PM’s Halloween Survival Guide

Discover the spooky parallels between Halloween and project management, from scope creep monsters to ghosted team members, in this fun survival guide for PMs.

R
Ronald B. Smith, MBA, PMP
2 months ago
Read
Explore All Articles