Back to ArticlesBack

Join 50,000+ PM Professionals

Get expert PM insights, PMP prep tips, and earn PDUs with exclusive content delivered weekly.

MPUG - Master Project User GroupMPUG - Master Project User Group

GAO_Schedule_Assessment_Guide_300_pixelsThe U.S. Government Accountability Office (GAO) has published a manual of best practices to help federal, state and local agencies to assess the schedules for government projects. The “Schedule Assessment Guide: Best Practices for Project Schedules,” available online, provides guidance for civilian and defense projects managed by either government entities or private contractors.

The new report uses content initially included in GAO’s March 2009 “Cost Estimating and Assessment Guide” and the draft “Schedule Assessment Guide” released for comment in 2012. The new 240-page document covers 10 best practices for developing and maintaining a reliable, high-quality schedule:

1. The schedule should capture all activities, as defined in the program’s work breakdown structure (WBS).

2. The schedule should be planned out so that critical program dates can be met. To do this, activities must be logically sequenced and linked — that is, listed in the order in which they are to be carried out and joined with logic.

3. The schedule should reflect the resources (labor, materials, travel, facilities, equipment and the like) for doing the work, whether they’ll be available when needed, as well as constraints on funding or time.

4. The schedule should realistically reflect how long each activity will take. When the duration of each activity is determined, the same rationale, historical data and assumptions used for cost estimating should be used. Durations should be reasonably short and meaningful and should allow for discrete progress measurement.

5. The schedule should be traceable both horizontally and vertically, meaning that it should link products and outcomes associated with other sequenced activities (horizontal); and data will be consistent between different levels of a schedule (vertical).

6. The schedule should identify the program’s critical path — the path of longest duration through the sequence of activities.

7. The schedule should identify reasonable total float (or slack) — the amount of time a predecessor activity can slip before the delay affects the program’s estimated finish date — so that the schedule’s flexibility can be determined.

8. A schedule risk analysis needs to start with a good critical path method schedule. Data about program schedule risks are incorporated into a statistical simulation to predict the level of confidence in meeting a program’s completion date; to determine the contingency, or reserve of time, needed for a level of confidence; and to identify high-priority risks.

9. Progress updates and logic should provide a realistic picture of start and completion dates for program activities.

10. A baseline schedule needs to form the basis for managing the program scope, the time period for accomplishing it and the required resources. The baseline schedule is designated the target schedule and is subjected to a configuration management control process. Program performance is measured, monitored and reported against the baseline schedule.

The guide includes extensive explanation for each practice as well as checklists and 19 separate case studies that illustrate how best practices can be applied.

“A well-planned schedule is an essential tool for program management,” said Gene Dodaro, comptroller general of the United States and head of the GAO, in a statement. “The best practices described in the guide are intended to help agencies create and maintain schedules that are comprehensive, well-constructed, credible and controlled.”

The “Schedule Assessment Guide: Best Practices for Project Schedules” is available for download from the GAO website here.

Get Weekly PM Insights

Join 50,000+ PMs receiving updates on the latest PM methodologies, PDU opportunities, tool reviews, career tips, and member exclusives.

PMI ATP
PMI Authorized Training Partner
REP #4082

Learning Paths

PMP® TrainingCAPM® TrainingPgMP® TrainingPMI-ACP® TrainingMS ProjectMS PlannerMS TeamsJira

PM Resources

PDU TrackerLive WebinarsSalary CalculatorTool ComparisonsJob BoardKnowledge BasePM Glossary

Community

Discussion ForumStudy GroupsEvents Calendar

Follow Us

LinkedInYouTubeTwitterFacebook
MPUG Logo

© 2026 MPUG. All rights reserved.

TermsPrivacySitemap
Articles

New GAO Guide Formalizes Scheduling Practices

The U.S. Government Accountability Office (GAO) has published a manual of best practices to help federal, state and local agencies to assess the schedules for government projects. The “Schedule Assessment […]

3 min read
•about 10 years ago•Updated 16 days ago•
T
The MPUG CommunityAuthor
Project Management
Microsoft Project
Best Practices
Productivity
T
The MPUG Community

Content Writer

MPUG has a global network of over 200,000 project management professionals across 170+ countries. For over 25 years, it has served as a premier platform fostering connection, knowledge sharing, and professional development within the project management community. MPUG champions the use of technology to optimize project management processes. It offers a comprehensive suite of resources and services, including live sessions, accredited training courses, informative lessons, industry articles, and interactive discussion forums. Committed to empowering its members to "Master Projects for Unlimited Growth," MPUG equips our members with the latest industry trends and propels their career advancement. Whether you're a budding project manager or a seasoned practitioner, MPUG provides an invaluable platform to hone your skills and bolster your project management expertise.

View all articles by The MPUG Community
Related Content

Continue Reading

Discover more insights and articles that complement your current reading

How Reserves Keep Projects Alive
Articles
4 min read

How Reserves Keep Projects Alive

Learn how project reserves protect your budget and schedule from unexpected risks, including when and how to use contingency, management, schedule, and cost reserves effectively.

R
Ronald B. Smith, MBA, PMP
12 days ago
Read
Why Platform Migrations Fail (And How to Land Yours Successfully)
Articles
4 min read

Why Platform Migrations Fail (And How to Land Yours Successfully)

Learn why platform migrations fail and how to land yours successfully using proven change management tactics for PMOs facing tool transitions like Project Online’s retirement.

T
The MPUG Community
15 days ago
Read
Beyond Project Online: Why Now Is the Time to Plan Your Move to Modern Portfolio Management and How We Can Help
Articles
5 min read

Beyond Project Online: Why Now Is the Time to Plan Your Move to Modern Portfolio Management and How We Can Help

Microsoft Project Online retires September 2026. Learn why now is the time to plan your transition to modern portfolio management and join our free webinar on January 28.

T
The MPUG Community
26 days ago
Explore All Articles
Read