ImageAs organizations work to improve their project management maturity level, they often develop methodologies that include standard processes and best practices. However, ensuring project managers consistently initiate new projects according to these standards and processes often proves challenging.

In a previous article I shared some tips for initiating a new project schedule easily and consistently with Project across an organization. In this article, I introduce some additional methods for initiating a new project.


Project Widgets CEO Ira Brown dives deeper into this topic in his MPUG webinar, “Best Practices for Initiating a New Project Schedule with Microsoft Project, Part 2,” available, on-demand.


Ira_Brown_Initiating_a_new_project_figure_1

When creating a new project based on an existing one, Microsoft Project treats the new project as if it were a template. And just as when initiating a project based on a template, there are several ways to update the project to reflect the requirements of the new project. Here are a few notes to keep in mind:

  • Adjust the values in the project’s Duration and Work fields for specific tasks, to reflect the new project’s focus.
  • When initiating a new project based on an existing in-progress or completed project, the new project won’t automatically reschedule because the tasks will frequently have Actual Start and Actual Finish dates. You must first remove the progress values from those tasks by setting % Complete for each task to “0”.
  • If the project contains any hard date constraints associated with any of the tasks (Must Start On, Must Finish On, etc.), you can clear the hard date constraints by setting them to As Soon as Possible or As Late as Possible

Additional Project Initiation Techniques

Some of the other techniques that can be used when initiating projects that align with organizational methodologies include the following:

  • Using the Import Project Wizard to transform a standalone MPP file into an enterprise project;
  • Replacing generic resources with named resources; and
  • Replacing generic resources with multiple named resources that will be fulfilling the same role.

Beyond these intrinsic Microsoft Project capabilities, the Project Initiation Widget add-on application from Project Widgets, takes this process to a new level. This software automates the new project creation process, leveraging existing project templates and metadata and providing project initiation flexibility through a dynamic user interface.

Get Weekly PM Insights

Join 50,000+ PMs receiving updates on the latest PM methodologies, PDU opportunities, tool reviews, career tips, and member exclusives.

Protected by reCAPTCHA: Privacy & Terms

PMI ATP
PMI Authorized Training Partner
REP #4082

Learning Paths

PMP® TrainingCAPM® TrainingPgMP® TrainingPMI-ACP® TrainingMS ProjectMS PlannerMS TeamsJira

PM Resources

PDU TrackerLive WebinarsSalary CalculatorTool ComparisonsJob BoardKnowledge BasePM GlossaryOur Faculty

Community

Discussion ForumStudy GroupsEvents Calendar

Follow Us

LinkedInYouTubeTwitterFacebook
MPUGMaster Project User Group

© 2026 MPUG. All rights reserved.

TermsPrivacySitemapAdvertise
Articles

More Tips for Creating a New Project Schedule in Microsoft Project

As organizations work to improve their project management maturity level, they often develop methodologies that include standard processes and best practices. However, ensuring project managers consistently initiate new projects according […]

2 min read
•almost 10 years ago•Updated 10 months ago•
I
Ira BrownAuthor
Project Management
Microsoft Project
Best Practices
Productivity
I
Ira Brown

Content Writer

Ira Brown is a leader in the field of project management and a recognized Microsoft Project expert, Project Widgets is well-known for offering add-on products for Microsoft Project and Project Online, as well as for creating custom solutions that meet their client's unique business requirements.  This company continues to extend the scope and breadth of their offerings, thereby increasing the value they provide to customers, by creating Microsoft Project solutions that are tailored to an organization's unique needs.  They even have several free, downloadable widgets available on their website that you can begin using right away.

View all articles by Ira Brown
Related Content

Continue Reading

Discover more insights and articles that complement your current reading

Collaboration challenges in remote projects (and how to fix each one)
Articles
1 min read

Collaboration challenges in remote projects (and how to fix each one)

Discover 5 common remote project collaboration challenges, from knowledge silos to unclear ownership, and learn practical ways to keep teams aligned and work moving.

A
Anonymous
7 days ago
Read
An Introduction to the PMI Practice Standard for Scheduling Conformance Index
Articles
1 min read

An Introduction to the PMI Practice Standard for Scheduling Conformance Index

Learn how the Conformance Index in PMI’s Practice Standard for Scheduling scores a CPM schedule model, and how to assess its components in any scheduling tool.

A
Anonymous
18 days ago
Read
A PM’s Halloween Survival Guide: The Sequel You Didn’t Want but Definitely Need
Articles
1 min read

A PM’s Halloween Survival Guide: The Sequel You Didn’t Want but Definitely Need

Part II of the PM Halloween survival guide takes on shape-shifting requirements and dependencies that won’t stay resolved, with practical defenses for each.

A
Anonymous
about 1 month ago
Read
Explore All Articles