ImageAs organizations work to improve their project management maturity level, they often develop methodologies that include standard processes and best practices. However, ensuring project managers consistently initiate new projects according to these standards and processes often proves challenging.

In a previous article I shared some tips for initiating a new project schedule easily and consistently with Project across an organization. In this article, I introduce some additional methods for initiating a new project.


Project Widgets CEO Ira Brown dives deeper into this topic in his MPUG webinar, “Best Practices for Initiating a New Project Schedule with Microsoft Project, Part 2,” available, on-demand.


Ira_Brown_Initiating_a_new_project_figure_1

When creating a new project based on an existing one, Microsoft Project treats the new project as if it were a template. And just as when initiating a project based on a template, there are several ways to update the project to reflect the requirements of the new project. Here are a few notes to keep in mind:

  • Adjust the values in the project’s Duration and Work fields for specific tasks, to reflect the new project’s focus.
  • When initiating a new project based on an existing in-progress or completed project, the new project won’t automatically reschedule because the tasks will frequently have Actual Start and Actual Finish dates. You must first remove the progress values from those tasks by setting % Complete for each task to “0”.
  • If the project contains any hard date constraints associated with any of the tasks (Must Start On, Must Finish On, etc.), you can clear the hard date constraints by setting them to As Soon as Possible or As Late as Possible

Additional Project Initiation Techniques

Some of the other techniques that can be used when initiating projects that align with organizational methodologies include the following:

  • Using the Import Project Wizard to transform a standalone MPP file into an enterprise project;
  • Replacing generic resources with named resources; and
  • Replacing generic resources with multiple named resources that will be fulfilling the same role.

Beyond these intrinsic Microsoft Project capabilities, the Project Initiation Widget add-on application from Project Widgets, takes this process to a new level. This software automates the new project creation process, leveraging existing project templates and metadata and providing project initiation flexibility through a dynamic user interface.

Get Weekly PM Insights

Join 50,000+ PMs receiving updates on the latest PM methodologies, PDU opportunities, tool reviews, career tips, and member exclusives.

PMI ATP
PMI Authorized Training Partner
REP #4082

Learning Paths

PMP® TrainingCAPM® TrainingPgMP® TrainingPMI-ACP® TrainingMS ProjectMS PlannerMS TeamsJira

PM Resources

PDU TrackerLive WebinarsSalary CalculatorTool ComparisonsJob BoardKnowledge BasePM Glossary

Community

Discussion ForumStudy GroupsEvents Calendar

Follow Us

LinkedInYouTubeTwitterFacebook
MPUG Logo

© 2026 MPUG. All rights reserved.

TermsPrivacySitemap
Articles

More Tips for Creating a New Project Schedule in Microsoft Project

As organizations work to improve their project management maturity level, they often develop methodologies that include standard processes and best practices. However, ensuring project managers consistently initiate new projects according […]

2 min read
•about 9 years ago•Updated 3 days ago•
I
Ira BrownAuthor
Project Management
Microsoft Project
Best Practices
Productivity
I
Ira Brown

Content Writer

Ira Brown is a leader in the field of project management and a recognized Microsoft Project expert, Project Widgets is well-known for offering add-on products for Microsoft Project and Project Online, as well as for creating custom solutions that meet their client's unique business requirements.  This company continues to extend the scope and breadth of their offerings, thereby increasing the value they provide to customers, by creating Microsoft Project solutions that are tailored to an organization's unique needs.  They even have several free, downloadable widgets available on their website that you can begin using right away.

View all articles by Ira Brown
Related Content

Continue Reading

Discover more insights and articles that complement your current reading

Why Platform Migrations Fail (And How to Land Yours Successfully)
Articles
4 min read

Why Platform Migrations Fail (And How to Land Yours Successfully)

Learn why platform migrations fail and how to land yours successfully using proven change management tactics for PMOs facing tool transitions like Project Online’s retirement.

M
Morgan Laubach
2 days ago
Read
Beyond Project Online: Why Now Is the Time to Plan Your Move to Modern Portfolio Management and How We Can Help
Articles
5 min read

Beyond Project Online: Why Now Is the Time to Plan Your Move to Modern Portfolio Management and How We Can Help

Microsoft Project Online retires September 2026. Learn why now is the time to plan your transition to modern portfolio management and join our free webinar on January 28.

T
The MPUG Community
13 days ago
Two Project Manager Agent Features You Might Like
Articles
5 min read

Two Project Manager Agent Features You Might Like

Discover two game-changing features of Microsoft’s Project Manager Agent including agent-to-agent communication and the new integrated interface in Planner.

E
Erik van Hurck
2 months ago
Read
Explore All Articles
Read