Microsoft Project provides the ability to integrate individual projects into a single master project. A master project, which is often used to represent a program, provides numerous capabilities to users, including the following:

  • View the master project and each of the subprojects it contains in a single schedule
  • Perform consolidated project reporting across the master project
  • Create interproject dependencies among the tasks in the master project

This article will provide a high-level overview of how to create a master project.

To create a master project, you can insert one or more projects into blank project file. For example, a software development master project might have subprojects for the development, testing, and training portions of this effort. The following instructions relate to this method.

Before beginning, you will need to identify separate Microsoft Project files for each project that is to become a subproject. For the master project, we will create new, blank project.

  1. Create a new blank project and apply the Gantt Chart view.
  2. Select the first task row in the blank project.
  3. In the Microsoft Project ribbon, select the Projects tab and click Subproject.

4. In the Insert Project dialog that displays, select the subproject to be inserted and click Insert.

Note that if you want to insert a subproject in a read-only format, you must first click the arrow on the Insert button, and then click Insert Read-Only. Inserting a project as read-only creates a link between two projects, but prevents users from updating a subproject from within the master project.

5. Repeat steps 3 and 4 to insert additional sub-projects into your master project.

Interested in learning more?

I dive deeper into this topic in my on-demand webinar, Working with Microsoft Project Master Schedules and Subprojects. I’ll show you how to create interproject dependencies and how to configure your master project properly so that you can specify how linked tasks are updated across subprojects in this PMI® PDU eligible session.

Get Weekly PM Insights

Join 50,000+ PMs receiving updates on the latest PM methodologies, PDU opportunities, tool reviews, career tips, and member exclusives.

Protected by reCAPTCHA: Privacy & Terms

PMI ATP
PMI Authorized Training Partner
REP #4082

Learning Paths

PMP® TrainingCAPM® TrainingPgMP® TrainingPMI-ACP® TrainingMS ProjectMS PlannerMS TeamsJira

PM Resources

PDU TrackerLive WebinarsSalary CalculatorTool ComparisonsJob BoardKnowledge BasePM Glossary

Community

Discussion ForumStudy GroupsEvents Calendar

Follow Us

LinkedInYouTubeTwitterFacebook
MPUG Logo

© 2026 MPUG. All rights reserved.

TermsPrivacySitemapAdvertise
Articles

Mastering Project Integration: Creating Master Projects in Microsoft Project

Microsoft Project provides the ability to integrate individual projects into a single master project. A master project, which is often used to represent a program, provides numerous capabilities to users, […]

2 min read
•over 5 years ago•Updated 3 months ago•
I
Ira BrownAuthor
Project Management
Microsoft Project
Best Practices
Productivity
I
Ira Brown

Content Writer

Ira Brown is a leader in the field of project management and a recognized Microsoft Project expert, Project Widgets is well-known for offering add-on products for Microsoft Project and Project Online, as well as for creating custom solutions that meet their client's unique business requirements.  This company continues to extend the scope and breadth of their offerings, thereby increasing the value they provide to customers, by creating Microsoft Project solutions that are tailored to an organization's unique needs.  They even have several free, downloadable widgets available on their website that you can begin using right away.

View all articles by Ira Brown
Related Content

Continue Reading

Discover more insights and articles that complement your current reading

Are You Running a Risk Meeting or a Risk Workshop?
Articles
1 min read

Are You Running a Risk Meeting or a Risk Workshop?

Learn the difference between a risk meeting and a risk workshop, and why structured risk workshops help project teams identify owners, define actions, and protect project outcomes.

A
Anonymous
4 days ago
Read
“I Need a Dashboard by Friday” – How AI Just Made That Possible
Articles
1 min read

“I Need a Dashboard by Friday” – How AI Just Made That Possible

Need a dashboard by Friday? Discover how AI tools like ChatGPT can help you build an Excel dashboard quickly and easily—no advanced technical skills required. Learn how to turn plain-English requests into real, working reports with spreadsheets that actually work for you.

A
Anonymous
4 days ago
Read
Why Tools Matter More Than Ever in Project Management (And Why Most Organizations Still Get Them Wrong)
Articles
1 min read

Why Tools Matter More Than Ever in Project Management (And Why Most Organizations Still Get Them Wrong)

Most PPM tools fail because they’re built for oversight, not adoption. Here’s how to design for decisions instead, and why Smartsheet bridges the gap.

A
Anonymous
6 days ago
Read
Explore All Articles