National Ignition Facility (NIF), a project sponsored by the U.S. Department of Energy’s (DOE) National Nuclear Security Administration (NNSA), has been awarded the The Project Management Institute’s (PMI)® Project of the Year Award. This award recognizes the work of a project team that shows superior performance, excellent project management execution, and innovation in the use of project management technology.

Laser Construction Wins PMI®'s Project of the Year AwardThe NIF, which was constructed at and led by the Lawrence Livermore National Laboratory in Livermore, CA, is the worlds largest and highest-energy laser. The project brought together representatives from governments, academia, and industry. It’s also the largest scientific construction project ever completed by the DOEs NNSA. The facility has the goal of achieving self-sustaining nuclear fusion in the laboratory for the first time. According to the DOE, fusion power has many of the benefits of long-term renewable energy sources, such as being a sustainable energy supply compared to presently utilized sources and emitting no greenhouse gases.

The project took 13 years. It was unitiated in 1996 and completed in March 2009. It consists of 192 giant lasers, housed in a 10-story building the size of three football fields, and capable of delivering at least 50 times more energy than any previous laser system. The facility contains more than 3,000 pieces of amplifier glass, 8,000 large optics, and 30,000 small optics that have been assembled into 6,206 replaceable units.

“We had a firm deadline for construction so equipment could be installed and completed,” said Edward Moses, principal associate director for the NIF and Photon Science Directorate at the lab. “It was imperative to have proper processes and standards in place so we could institute a high level of technical and scientific project integration with an international, interdisciplinary consortium of scientists, engineers, vendors and suppliers. We are honored that PMI recognized the hard work, collaboration and dedication of the entire team that worked to create NIF.”

The project was completed three weeks ahead of schedule and about $2 million under budget.

The award was presented this week during PMI®’s Global Congress in Washington, DC.

Photo credit: Lawrence Livermore National Laboratory

Get Weekly PM Insights

Join 50,000+ PMs receiving updates on the latest PM methodologies, PDU opportunities, tool reviews, career tips, and member exclusives.

Protected by reCAPTCHA: Privacy & Terms

PMI ATP
PMI Authorized Training Partner
REP #4082

Learning Paths

PMP® TrainingCAPM® TrainingPgMP® TrainingPMI-ACP® TrainingMS ProjectMS PlannerMS TeamsJira

PM Resources

PDU TrackerLive WebinarsSalary CalculatorTool ComparisonsJob BoardKnowledge BasePM GlossaryOur Faculty

Community

Discussion ForumStudy GroupsEvents Calendar

Follow Us

LinkedInYouTubeTwitterFacebook
MPUGMaster Project User Group

© 2026 MPUG. All rights reserved.

TermsPrivacySitemapAdvertise
Articles

Laser Construction Wins PMI®’s Project of the Year Award

National Ignition Facility (NIF), a project sponsored by the U.S. Department of Energy’s (DOE) National Nuclear Security Administration (NNSA), has been awarded the The Project Management Institute’s (PMI)® Project of the […]

2 min read
•about 16 years ago•Updated 10 months ago•
M
MPUGAuthor
Project Management
Microsoft Project
Best Practices
Productivity
M
MPUG

Content Writer

View all articles by MPUG
Related Content

Continue Reading

Discover more insights and articles that complement your current reading

Collaboration challenges in remote projects (and how to fix each one)
Articles
1 min read

Collaboration challenges in remote projects (and how to fix each one)

Discover 5 common remote project collaboration challenges, from knowledge silos to unclear ownership, and learn practical ways to keep teams aligned and work moving.

A
Anonymous
1 day ago
Read
An Introduction to the PMI Practice Standard for Scheduling Conformance Index
Articles
1 min read

An Introduction to the PMI Practice Standard for Scheduling Conformance Index

Learn how the Conformance Index in PMI’s Practice Standard for Scheduling scores a CPM schedule model, and how to assess its components in any scheduling tool.

A
Anonymous
13 days ago
Read
A PM’s Halloween Survival Guide: The Sequel You Didn’t Want but Definitely Need
Articles
1 min read

A PM’s Halloween Survival Guide: The Sequel You Didn’t Want but Definitely Need

Part II of the PM Halloween survival guide takes on shape-shifting requirements and dependencies that won’t stay resolved, with practical defenses for each.

A
Anonymous
about 1 month ago
Read
Explore All Articles