Back to ArticlesBack

Join 50,000+ PM Professionals

Get expert PM insights, PMP prep tips, and earn PDUs with exclusive content delivered weekly.

Protected by reCAPTCHA: Privacy & Terms

MPUG - Master Project User GroupMPUG

Sensei_book_imageSynergize

What is synergy? Stephen Covey defines it this way: “It means the whole is greater than the sum of its parts. It means that the relationship which the parts have to each other is a part in and of itself.”

Once all the pieces of the schedule have been put together properly and are in line with industry standards, the schedule becomes greater than the sum of its parts. It will now truly represent the actual project and will enable the project manager to be proactive and provide executives with critical information for decision making. If a project experiences delays or overruns, a proactive schedule will give early warning and help identify the best options for corrective actions.

Synergy on the project team will also allow team members to participate actively in any corrective action required. Techniques such as crashing and fast tracking are much more successful with a synergistic project team and easier to apply in a proactive project schedule.

This excerpt is from the new book, Proactive PPM with Microsoft Project 2016 for Project Online and Project Server: A best practices guide for project managers, written by Kenneth Steiness and Dale Howard and published by Sensei Project Solutions.

Read “Habit 1: Be Proactive” here.

Read “Habit 2: Begin with the End in Mind” here.

Read “Habit 3: Put First Things First” here.

Read “Habit 4: Think Win-Win” here.

Read “Habit 5: Seek First to Understand, Then to Be Understood” here.

Read “Habit 7: Sharpen the Saw” here.


Written by Kenneth Steiness

Kenneth-Steiness_avatar_1456165080-120x120Kenneth Steiness PMP/PMI-SP MCP MCT is an industry expert on Microsoft Project and Project Server and has worked in the project management and scheduling field for over 16 years. He has managed customer engagements in over 13 countries worldwide and throughout the United States, in addition to presenting at world-wide conferences for Microsoft, PMI, and to many Microsoft Project User Groups over the years. Kenneth is the Managing Partner & VP of Delivery of Sensei Project Solutions, a Microsoft Partner specializing in Project and Portfolio Management (PPM) deployments with Microsoft Project and Project Server on the SharePoint platform. Sensei offers a complete set of services to help an organization make their Microsoft PPM deployment successful, including full implementation and services, training as well as pre-configured solutions and report packs. Visit senseiprojectsolutions.com or contact info@senseiprojectsolutions.com for more information.

View all posts by: Kenneth Steiness


Get Weekly PM Insights

Join 50,000+ PMs receiving updates on the latest PM methodologies, PDU opportunities, tool reviews, career tips, and member exclusives.

Protected by reCAPTCHA: Privacy & Terms

PMI ATP
PMI Authorized Training Partner
REP #4082

Learning Paths

PMP® TrainingCAPM® TrainingPgMP® TrainingPMI-ACP® TrainingMS ProjectMS PlannerMS TeamsJira

PM Resources

PDU TrackerLive WebinarsSalary CalculatorTool ComparisonsJob BoardKnowledge BasePM GlossaryOur Faculty

Community

Discussion ForumStudy GroupsEvents Calendar

Follow Us

LinkedInYouTubeTwitterFacebook
MPUGMaster Project User Group

© 2026 MPUG. All rights reserved.

TermsPrivacySitemapAdvertise
Articles

The 7 Habits of Proactive Microsoft PPM Users: Habit 6

Synergize What is synergy? Stephen Covey defines it this way: “It means the whole is greater than the sum of its parts. It means that the relationship which the parts […]

2 min read
•almost 10 years ago•Updated 10 months ago•
K
Kenneth SteinessAuthor
Project Management
Microsoft Project
Best Practices
Productivity
K
Kenneth Steiness

Content Writer

Kenneth Steiness, PMP, PMI-SP, MCP, MCT, is an industry expert on Microsoft Project and Project Online. Kenneth has worked in the project management and scheduling field for over 20 years. He has managed customer engagements in 13 countries and throughout the United States and presented at conferences world-wide for Microsoft, PMI and MPUG. Kenneth is the CEO of Sensei Project Solutions, a certified Microsoft partner specializing in project and portfolio management deployments. Sensei offers a complete set of services to help organizations succeed with their Microsoft PPM deployments. Services include full implementation and training as well as pre-configured solutions and report packs. Visit senseiprojectsolutions.com or contact info@senseiprojectsolutions.com for more information.

View all articles by Kenneth Steiness
Related Content

Continue Reading

Discover more insights and articles that complement your current reading

An Introduction to the PMI Practice Standard for Scheduling Conformance Index
Articles
1 min read

An Introduction to the PMI Practice Standard for Scheduling Conformance Index

Learn how the Conformance Index in PMI’s Practice Standard for Scheduling scores a CPM schedule model, and how to assess its components in any scheduling tool.

A
Anonymous
3 days ago
Read
A PM’s Halloween Survival Guide: The Sequel You Didn’t Want but Definitely Need
Articles
1 min read

A PM’s Halloween Survival Guide: The Sequel You Didn’t Want but Definitely Need

Part II of the PM Halloween survival guide takes on shape-shifting requirements and dependencies that won’t stay resolved, with practical defenses for each.

A
Anonymous
21 days ago
Read
Context Engineering for Project Managers: Give AI the Project, Not Just the Question
Articles
1 min read

Context Engineering for Project Managers: Give AI the Project, Not Just the Question

Learn how to choose, date, and source the project information you give AI, so its risk analyses, status reports, and change request reviews reflect your actual project.

A
Anonymous
about 1 month ago
Read
Explore All Articles