Back to ArticlesBack

Join 50,000+ PM Professionals

Get expert PM insights, PMP prep tips, and earn PDUs with exclusive content delivered weekly.

Protected by reCAPTCHA: Privacy & Terms

MPUG - Master Project User GroupMPUG

In Part One, I presented a simple method to identify, quantify, and evaluate risk in projects and tasks. In this article, I will create a “Risk Assessment Dashboard” in Microsoft Project that’s based on that method.

When completed it will look like this:

dashboard_1

I will create the “Risk Assessment Dashboard” in four steps:

Step 1: Create the “Risk Assessment” table

1) Click on the “View” tab.

2) In the “Data” group, click on “Tables”.

3) At the bottom of the “Tables” list click on “More Tables…”

dashboard_2

4) The “More Tables” dialog appears. Click on the “New…” button.

dashboard_3

5) The “Table Definition” dialog appears. Enter data into this as is indicated in the figure below, then click on “OK”.

dashboard_4

When a new table is created, Project places the table at the top of the table list so it is easy to apply. See the figure below.

dashboard_5


Want more Do’s and Don’ts? Check out MPUG’s new book: Microsoft® Project Do’s and Don’ts!


Now on to the next step.

Step 2: Create the two custom field lookup tables

1) Click on the “Project” tab.

2) In the “Properties” group, click on “Custom Fields”.

3) The “Custom Fields” dialog appears. The “Text1” field needs a name more descriptive of its function. Select “Text1” from the field list in the dialog and then click on the “Rename” button just under the list.

4) The “Rename Field” dialog appears. Rename the field “Probability(1…5) as is shown in the figure below.

dashboard_6

5) Click on the “OK” button in the “Rename Field” dialog to return to the “Custom Fields” dialog.

6) In the “Custom Attributes” section of the “Custom Fields” dialog, click on the “Lookup…” button.

7) The “Edit Lookup Table for Probability (1…5)” dialog will appear. This dialog will contain the levels of probability and what they mean. Enter the levels as shown in the figure below.

dashboard_7

8) Click on the “Close” button in the lower right corner of the dialog. This returns you to the “Custom Fields” dialog.

9) Click on “OK” to close the dialog.

10) Note that the “Text1” field is now ”Probability (1…5)” and that every cell in the field contains a drop down listing of the levels of probability and what the number means. Project will still maintain the original field name as well as the new name.

dashboard_8

11) Repeat 1 through 9 for the “Text2” field, but rename it “Impact (1…5)”.  Once both fields are created, it’s  on to the next step.

Step 3: Create two formula fields

The “Text3” and “Text4” fields do the math and quantify the risk for the graphical indicators. Each will have to be customized.

1) For the “Text3” field follow steps 1 – 5, but give the field the new name “Risk Level (Prob X Impact, Max = 25)”.

2) In the “Custom Fields” dialog, in the “Custom Attributes” section, click on “Formula…”.

3) The formula editor will appear for the new “Risk Level…” field. Enter this formula (without the quotes): “[Probability (1…5)] * [Impact (1..5)]”. Alternatively, the editor contains MS Project’s fields for selection and inclusion in the formula. It now should look like the figure below.

dashboard_9

4) Click on “OK” to set the formula, and click on “OK” in the “Custom Fields” dialog to set the field customizations. If the field returns “#ERROR”, it is because there is no data to evaluate yet. Test the field and results by choosing the value “2” from the two custom field lookup table. The result should be “4”.

5) Repeat 1 – 2 above, but rename “Text4” to “Risk Severity”. This field will contain a formula that associates the risk to a High, Medium or Low threat. The field will evaluate per the rules in the table below.

dashboard_10

6) Repeat 3 above with the formula “IIf([Text3]>14,”High”,IIf([Text3]>5 And [Text3]<14,”Medium”,”Low”))”. Note that I used the actual field name in this formula. I could have used the new names instead. Both are valid.

The final step will associate the graphical indicators with “Risk Severity”.

Step 4: Create graphical Indicators

1) Return to the “Risk Severity” fields’ “Custom Field” dialog.

2) Near the bottom of the dialog, in the “Values to display” section, click on “Graphical Indicators” as shown in the figure below.

dashboard_11

3) The “Graphical Indicators” dialog appears.  The goal is to have an indicator for “Low”, “Medium” and “High”. This will associate the correct color to each risk level. The figure below illustrates the syntax and selections you should make.

dashboard_12

4) Click “OK” to set and close the “Graphical Indicators” dialog. Click on “OK” again to set and close the “Custom Field” dialog.

Test the new table out by entering a few tasks and using the probability and impact fields to associate different levels of risk. It should give you information similar to the figure below.

dashboard_13

Once the work is done to create the “Risk Assessment Dashboard,” edit the graphical indicators to work in Summary tasks and in the Project Summary Task. This action will enable you to represent and manage risk at any level in your project!

In the next article, I will use the fields, the formula, and the graphical indicators from this article to report on risk. I will illustrate filtering and grouping risk and how to summarize the cost. work and schedule that is developed in the project so far.

Get Weekly PM Insights

Join 50,000+ PMs receiving updates on the latest PM methodologies, PDU opportunities, tool reviews, career tips, and member exclusives.

Protected by reCAPTCHA: Privacy & Terms

PMI ATP
PMI Authorized Training Partner
REP #4082

Learning Paths

PMP® TrainingCAPM® TrainingPgMP® TrainingPMI-ACP® TrainingMS ProjectMS PlannerMS TeamsJira

PM Resources

PDU TrackerLive WebinarsSalary CalculatorTool ComparisonsJob BoardKnowledge BasePM GlossaryOur Faculty

Community

Discussion ForumStudy GroupsEvents Calendar

Follow Us

LinkedInYouTubeTwitterFacebook
MPUGMaster Project User Group

© 2026 MPUG. All rights reserved.

TermsPrivacySitemapAdvertise
Articles

Microsoft® Project Do’s and Don’ts: Creating a Risk Assessment Dashboard: Part 2

In Part One, I presented a simple method to identify, quantify, and evaluate risk in projects and tasks. In this article, I will create a “Risk Assessment Dashboard” in Microsoft […]

4 min read
•about 12 years ago•Updated 10 months ago•
S
Sam HuffmanAuthor
Project Management
Microsoft Project
Best Practices
Productivity
S
Sam Huffman

Content Writer

Sam Huffman first gained insight into Microsoft Project while working as a member of the MS Project development and support team. He has maintained his depth of knowledge of MS Project with each release and is a leading authority in the use and features of MS Project, Project Server and Project Online. Since the early 1990's Sam has honed his instruction skills by delivering training programs to thousands every year. Sam is a frequent content contributor to the Microsoft Project User Group (MPUG) and speaks to groups often about MS Project, Enterprise Project Management and the discipline of Project Management. He was awarded Microsoft Most Valuable Professional from 2010-2017. Check out his blog on MS Project. The softcover version of my newest book Microsoft® Project Do’s and Don’ts is now available for purchase! It is portable, brief and to the point so you can find help when you need it. Through tips, best practices and examples it will help you jumpstart your project!

View all articles by Sam Huffman
Related Content

Continue Reading

Discover more insights and articles that complement your current reading

Collaboration challenges in remote projects (and how to fix each one)
Articles
1 min read

Collaboration challenges in remote projects (and how to fix each one)

Discover 5 common remote project collaboration challenges, from knowledge silos to unclear ownership, and learn practical ways to keep teams aligned and work moving.

A
Anonymous
7 days ago
Read
An Introduction to the PMI Practice Standard for Scheduling Conformance Index
Articles
1 min read

An Introduction to the PMI Practice Standard for Scheduling Conformance Index

Learn how the Conformance Index in PMI’s Practice Standard for Scheduling scores a CPM schedule model, and how to assess its components in any scheduling tool.

A
Anonymous
18 days ago
Read
A PM’s Halloween Survival Guide: The Sequel You Didn’t Want but Definitely Need
Articles
1 min read

A PM’s Halloween Survival Guide: The Sequel You Didn’t Want but Definitely Need

Part II of the PM Halloween survival guide takes on shape-shifting requirements and dependencies that won’t stay resolved, with practical defenses for each.

A
Anonymous
about 1 month ago
Read
Explore All Articles