Back to ArticlesBack

Join 50,000+ PM Professionals

Get expert PM insights, PMP prep tips, and earn PDUs with exclusive content delivered weekly.

Protected by reCAPTCHA: Privacy & Terms

MPUG - Master Project User GroupMPUG - Master Project User Group

Oh, the misery! If you’ve ever used Fixed Duration tasks in your enterprise projects running in Microsoft Project Online or Project Server and your organization uses the Timesheet page in Project Web App (PWA) to track actual task progress, then no doubt you have experienced heartache and disappointment. Those Fixed Duration tasks don’t behave the way they’re supposed to. You know I’m speaking the truth if you’ve ever seen this Microsoft Project warning dialog:

(Memorize this screenshot. You’d be seeing it a lot if you were the project manager in the following scenarios.)

Most project managers assume that using Fixed Duration tasks will guarantee that the Duration and Finish date won’t change for these tasks. Unfortunately, nothing could be further from the truth!

There are multiple scenarios that can cause the Duration and/or the Finish date to change on a Fixed Duration task. These scenarios include (but aren’t limited to) the following:

  • Scenario #1. A team member submits planned nonworking time (such as vacation) for a period between the Start date and Finish date of the task.
  • Scenario #2. A team member enters an initial Actual Work value on a date later than the Start date of the task when the task has multiple resources assigned.
  • Scenario #3. A team member increases the Remaining Work value after completing all the planned work on the task.
  • Scenario #4. A team member doesn’t finish the planned work by the Finish date of the task.
  • Scenario #5. A team member enters an Actual Work value on a date later than the Finish date of the task.
  • Scenario #6. A team member enters task progress earlier than the Start date of a task that has a Finish No Earlier Than (FNET) or Must Finish On (MFO) constraint applied.
  • Scenario #7. The project manager reschedules uncompleted work from the past into the current reporting period.

Scenario #1. Planned Vacation

The next screenshot shows the sample project I use in this article. Notice that Calvin Baker is assigned to Task A. This Fixed Duration task has a Duration of 10 days and a Finish date of June 16.

Calvin submits a week of planned vacation as nonworking time on his Timesheet in PWA for June 12-16. The next time this enterprise project is opened, the project manager will see the warning dialog I showed previously. The next figure shows the Gantt Chart view of the project that reveals the impact of Calvin’s vacation. Notice that the Duration of this Fixed Duration task has changed from 10 days to 15 days, and the Finish date has slipped from June 16 to June 23.

Scenario #2. Actual Start is Later Than the Planned Start

Task B is a Fixed Duration task with a Duration of 10 days and a Finish date of June 16. Using the Timesheet page in PWA, team members submitted their Actual Work for their Task B assignments for the week of June 4, as shown in the next screenshot. Notice that Cindy McNair submitted two hours of Actual Work for each day of the week. Notice also that Jerry King submitted two hours of Actual Work only on Friday, a date that is four days later than the expected Start date of his assignment work on this task.

After approving the task updates, the project manager will get the warning dialog when the enterprise project is opened. Because Jerry started his assignment work four days later than originally scheduled on this Fixed Duration task, Project has changed both the Duration and the Finish date of this task, as shown in the next figure. Notice that the Duration has increased from 10 days to 14 days and the Finish date has slipped from June 16 to June 22.

The next screenshot shows the Task Usage view for Task B, with the last two weeks of planned Work displayed in the time-phased grid. Notice how Jerry’s planned Work slips four days into the week of June 18. This slippage is a result of Jerry starting four days late on his assignment work for this task, which caused the Duration to increase by four days and the Finish date to slip by four days as well.

Scenario #3. Remaining Work Increase

Task C is a Fixed Duration task with a Duration of two days and a Finish date of June 6. On his Task C task assignment, Larry Barnes was originally assigned to work eight hours each day on Monday and Tuesday of the week of June 4. Using the Timesheet page in PWA, Larry Barnes entered eight hours of Actual Work on Monday and Tuesday, which caused the Remaining Work to drop to zero hours. Larry increased the Remaining Work to 16 hours because he still hadn’t completed the task, and then submitted the update to his project manager. You can see his task update for this assignment in the next figure.

After approving the task update from Larry, the project manager opened the enterprise project. Project displayed its warning dialog. The next image shows the Gantt chart view for Task C. Notice that the Duration of this Fixed Duration task has increased from two days to four days, and the Finish date has slipped from June 6 to June 8.

Scenario #4. Actual Work Behind Schedule

Task D is a Fixed Duration task with a Duration of two days and a Finish date of June 6. On her Task D task assignment, Linda Erickson was originally assigned to work eight hours each day on Monday and Tuesday of the week of June 4. Using the Timesheet page in PWA, Linda entered only four hours of Actual Work each day on Monday and Tuesday and then submitted the task update to her project manager. You can see her task update for this assignment in the next figure. Notice that her eight hours of uncompleted Work has been rescheduled to Wednesday of that week.

After approving the task update from Linda, the project manager opened the enterprise project and saw the warning dialog. The next screenshot shows the Gantt Chart view for Task D. Notice that the Duration of this Fixed Duration task has increased from two days to three days, and the Finish date has slipped from June 6 to June 7.

Scenario #5. Actual Work Past the Finish Date

Task E is a Fixed Duration task with a Duration of two days and a Finish date of June 6. On her Task E task assignment, Marcia Bickel was originally assigned to work eight hours each day on Monday and Tuesday of the week of June 4. Using the Timesheet page in PWA, Marcia entered eight hours of Actual Work each day during all five days of the week and then submitted the task update to her project manager. You can see her task update for this assignment here:

After approving the task update from Marcia, the project manager opened the enterprise project and received the warning dialog. The next figure shows the Gantt chart view for Task E. Notice that the Duration of this Fixed Duration task has increased from two days to five days, and the Finish date has slipped from June 6 to June 9.

Scenario #6. Early Progress on a Constrained Task

Task F is a Fixed Duration task with a Duration of 10 days, a Start date of June 12 and a Finish date of June 23. This task has a Finish No Earlier Than (FNET) constraint applied with a constraint date of Friday, June 23, which means that the task can’t finish earlier than that date.

On her Task F task assignment, Mickey Cobb was originally scheduled to start work on Monday, June 12. Because of an early finish on a task in another project, Mickey Cobb could start early on her Task F assignment on Friday, June 9. Using the Timesheet page in PWA, Mickey Cobb entered eight hours of Actual Work on Friday, June 9 and submitted the task update to her project manager. You can see her task update for this assignment here:

After approving the task update from Mickey, the project manager opened the enterprise project. In this situation, however, Project hasn’t displayed the warning dialog we’ve come to know so well. The next screenshot shows the Gantt Chart view for the Task F task. Even though the software doesn’t show the warning dialog, notice the Duration of this Fixed Duration task has increased from 10 days to 11 days and the Start date of the task has changed from June 12 to June 9.

Scenario #7. Reschedule Uncompleted Work

Task G has a Duration of 10 days and a Finish date of June 16. Susan Tartaglia and Terry Uland were each originally scheduled to work 40 hours on this task during the week of June 4. However, they could complete work only on Monday and Tuesday before they were pulled off this project to help with a higher priority project. Using the Timesheet page in PWA, Susan and Terry each entered eight hours of Actual Work on Monday and Tuesday, June 5-6, and then submitted their task updates to their project manager. You can see the task updates for their assignments in the next image.

After approving the task updates from Susan and Terry, the project manager opened the enterprise project. The following screenshot shows the Gantt Chart view of the project with the task updates applied on Task G. By the way, the red dotted line in the Gantt Chart pane is the Status Date line.

Because Task G now has three days of uncompleted work in the past (work scheduled to the left of the Status Date line), the project manager rescheduled the uncompleted work into the next week using the Update Project dialog. Once again, Project won’t display the warning dialog. The next figure shows the Gantt Chart view for the Task G task after rescheduling uncompleted work from the past. Notice that the Duration of this Fixed Duration task has increased from 10 days to 13 days, and the Finish date has slipped from June 16 to June 21.

A Final Recommendation

I have now documented at least seven situations that can cause the Duration to increase and the Finish date to slip for Fixed Duration tasks. If your organization is using the Timesheet page to capture task progress in the Microsoft PPM solution, Project Online or Project Server, then I advise against using Fixed Duration tasks in your enterprise projects. To eliminate the confusion and the frustration caused by Fixed Duration task behavior, my recommendation is that you use either Fixed Work or Fixed Units tasks instead.

Get Weekly PM Insights

Join 50,000+ PMs receiving updates on the latest PM methodologies, PDU opportunities, tool reviews, career tips, and member exclusives.

Protected by reCAPTCHA: Privacy & Terms

PMI ATP
PMI Authorized Training Partner
REP #4082

Learning Paths

PMP® TrainingCAPM® TrainingPgMP® TrainingPMI-ACP® TrainingMS ProjectMS PlannerMS TeamsJira

PM Resources

PDU TrackerLive WebinarsSalary CalculatorTool ComparisonsJob BoardKnowledge BasePM Glossary

Community

Discussion ForumStudy GroupsEvents Calendar

Follow Us

LinkedInYouTubeTwitterFacebook
MPUG Logo

© 2026 MPUG. All rights reserved.

TermsPrivacySitemapAdvertise
Articles

When a Fixed Duration Task is Truly Not “Fixed Duration”

Oh, the misery! If you’ve ever used Fixed Duration tasks in your enterprise projects running in Microsoft Project Online or Project Server and your organization uses the Timesheet page in […]

8 min read
•over 8 years ago•Updated 3 months ago•
D
Dale HowardAuthor
Project Management
Microsoft Project
Best Practices
Productivity
D
Dale Howard

Content Writer

Dale Howard is currently a Senior PPM Consultant with Arch Systems, Inc. His hair and beard have turned white because of using Microsoft's project management tools for more than 20 years. Dale started his career using Microsoft Project 4.0 for Windows 95 and began using Microsoft's PPM tools when they introduced Project Central in 2000. Dale is the co-author of 23 books in Microsoft Project, Project Server, and Project Online. He is currently one 0f 26 Microsoft Project MVPs in the entire world and one of only 4 Project MVPs in the United states.

View all articles by Dale Howard
Related Content

Continue Reading

Discover more insights and articles that complement your current reading

5 Ways to Get More Value from Your Microsoft Project Desktop Data
Articles
1 min read

5 Ways to Get More Value from Your Microsoft Project Desktop Data

Discover five ways to extend your Microsoft Project Desktop data into reporting, automation, and the Power Platform — without disrupting project managers.

A
Anonymous
4 days ago
Read
The Toilet Paper Rule: Why Small Problems Become Big Failures
Articles
1 min read

The Toilet Paper Rule: Why Small Problems Become Big Failures

Ronald B. Smith uses the humble toilet paper roll to unpack six enduring truths about preparation, quality, and the invisible work of project management.

A
Anonymous
10 days ago
Read
Are You Running a Risk Meeting or a Risk Workshop?
Articles
1 min read

Are You Running a Risk Meeting or a Risk Workshop?

Learn the difference between a risk meeting and a risk workshop, and why structured risk workshops help project teams identify owners, define actions, and protect project outcomes.

A
Anonymous
17 days ago
Read
Explore All Articles