Sometimes managers and executives want to know only the basic status of a task or project. Questions like “Has it started?” or “Is it done?” are not calling for a detailed analysis of whether performance is going as planned. They are quick questions demanding a quick answer.

I am going to show you how to create a “Kanban Board” that gives at-a-glance answers to those basic questions. It looks like this in Project:

The “Kanban Board” clearly shows what is completed, what is in progress, and what is not started. If your organization uses Agile techniques in managing projects, you will recognize the “Kanban Board” as a tool to help you and your management team manage workflow in projects.

The “Kanban” technique was originally imagined by Toyota to capture workflow. It can have more than the three states used in this example depending on need and preference. Conduct a web search on “Kanban” to get more details on this excellent technique.

In its simplest form, a “Kanban Board” look like this:

Note that the “Simple Kanban Board” and the “Kanban Board” shown in Project contain similar information. The difference between the two is that one is a formula-driven table in Microsoft Project while the other is yellow sticky notes. Both work, but by incorporating the Project table a complete schedule can be managed at any level during the project’s life cycle.

The “Kanban Board” avoids graphic details such as those found in the “Tracking Gantt”:

Note that the project file used for this blog entry is actually a small portfolio of projects organized by departments. For the sake of clarity dedicated resources from each department are assigned to their department’s projects. The Tracking Gantt gives detailed information regarding slipping tasks, performance to plan, variance and even illustrates the critical path. These are obviously important details, but are not the focus of the “Kanban Board.”

In order to create a “Kanban Board” in Microsoft Project a small amount of customization has to be done. A custom field, a custom view and a custom group all interrelate and give you this simple and effective tool.

The custom field should be an unused text field. This is critical! You will overwrite existing data if you choose a text field already in use.

In part 2 of this article, I show you how.

Check out the full Do’s and Don’ts Boot Camp!

Get Weekly PM Insights

Join 50,000+ PMs receiving updates on the latest PM methodologies, PDU opportunities, tool reviews, career tips, and member exclusives.

Protected by reCAPTCHA: Privacy & Terms

PMI ATP
PMI Authorized Training Partner
REP #4082

Learning Paths

PMP® TrainingCAPM® TrainingPgMP® TrainingPMI-ACP® TrainingMS ProjectMS PlannerMS TeamsJira

PM Resources

PDU TrackerLive WebinarsSalary CalculatorTool ComparisonsJob BoardKnowledge BasePM GlossaryOur Faculty

Community

Discussion ForumStudy GroupsEvents Calendar

Follow Us

LinkedInYouTubeTwitterFacebook
MPUGMaster Project User Group

© 2026 MPUG. All rights reserved.

TermsPrivacySitemapAdvertise
Articles

Do’s and Don’ts: Use a Kanban Board! (Part 1)

From the author of Microsoft Project Do’s and Don’ts. Check out the NEW Do’s and Don’ts Bootcamp, which delivers Microsoft Project Management proficiency (and credibility) in just three hours of […]

2 min read
•about 8 years ago•Updated 10 months ago•
S
Sam HuffmanAuthor
Project Management
Microsoft Project
Best Practices
Productivity
S
Sam Huffman

Content Writer

Sam Huffman first gained insight into Microsoft Project while working as a member of the MS Project development and support team. He has maintained his depth of knowledge of MS Project with each release and is a leading authority in the use and features of MS Project, Project Server and Project Online. Since the early 1990's Sam has honed his instruction skills by delivering training programs to thousands every year. Sam is a frequent content contributor to the Microsoft Project User Group (MPUG) and speaks to groups often about MS Project, Enterprise Project Management and the discipline of Project Management. He was awarded Microsoft Most Valuable Professional from 2010-2017. Check out his blog on MS Project. The softcover version of my newest book Microsoft® Project Do’s and Don’ts is now available for purchase! It is portable, brief and to the point so you can find help when you need it. Through tips, best practices and examples it will help you jumpstart your project!

View all articles by Sam Huffman
Related Content

Continue Reading

Discover more insights and articles that complement your current reading

Collaboration challenges in remote projects (and how to fix each one)
Articles
1 min read

Collaboration challenges in remote projects (and how to fix each one)

Discover 5 common remote project collaboration challenges, from knowledge silos to unclear ownership, and learn practical ways to keep teams aligned and work moving.

A
Anonymous
8 days ago
Read
An Introduction to the PMI Practice Standard for Scheduling Conformance Index
Articles
1 min read

An Introduction to the PMI Practice Standard for Scheduling Conformance Index

Learn how the Conformance Index in PMI’s Practice Standard for Scheduling scores a CPM schedule model, and how to assess its components in any scheduling tool.

A
Anonymous
19 days ago
Read
A PM’s Halloween Survival Guide: The Sequel You Didn’t Want but Definitely Need
Articles
1 min read

A PM’s Halloween Survival Guide: The Sequel You Didn’t Want but Definitely Need

Part II of the PM Halloween survival guide takes on shape-shifting requirements and dependencies that won’t stay resolved, with practical defenses for each.

A
Anonymous
about 1 month ago
Read
Explore All Articles