Back to ArticlesBack

Join 50,000+ PM Professionals

Get expert PM insights, PMP prep tips, and earn PDUs with exclusive content delivered weekly.

Protected by reCAPTCHA: Privacy & Terms

MPUG - Master Project User GroupMPUG

Ron from Cleveland, OH asks: Is it a good practice or bad to link summary tasks?

Answer: In general I don’t believe that it’s a best practice to link summary tasks within a work breakdown structure (WBS). Here are some of the reasons:

  • It’s the detail tasks and the milestones that move a schedule ahead and not the summaries. Summaries can’t be tracked and shouldn’t have resources assigned to them. They’re not real tasks so much as subtotals and/or titles.
  • If you try to track a summary task, it will be right only when there’s either zero percent or 100 percent completed on the detail tasks. This occurs because there’s a consistent recalculation of the summary task totals by default based on changes to their member tasks.
  • Linking summaries can cause errors in the schedule that might be hard to trace.
  • Linking summaries means that the entire grouping of tasks must be completed before the next grouping can start.

This last point brings up an interesting idea: Consider the application of some agile-based Scrum scheduling methodology to your project management efforts. In Scrum, a sprint (a period of two to four weeks) is always completed within a set timeframe before the next sprint can start. If any of the work in the first sprint doesn’t get completed, that work is moved over to the subsequent sprint. Each sprint is made up of “stories,” tasks scheduled to be completed in that two-, three-, or four-week section.

I would recommend using the WBS structure with milestones at the end of each summary grouping, as shown in Figure 1. The tasks within the groupings should be linked to the ending milestones because completion has the ability to push the milestones. Using this structure will also allow for generation of milestone or summary management reports in order to show the progress of the sprints.

Note that I’ve placed a deadline after each milestone. During tracking of the tasks, the goal is to ensure that the milestone arrow won’t cross the green arrow (deadline) if it does, the scheduler will be alerted. In addition, adding the deadline will allow users to monitor the total slack column to see when the slack goes negative and they’re approaching the danger of missing a deadline.

Also during tracking, if the remaining work for a task is increased, the result could be that the schedule is pushed past the two-, three-, or four-week gates and the deadline indicators would alert the scheduler to this problem as well.

Figure 1: Applying Scrum development techniques to project scheduling.

Lehnert081709_1

Figure 2 shows an example of the rolled up milestone report, which could be used for management reporting. To apply the milestone filter, click on Project | Filtered for | Milestone. To remove the filter, press the F3 key.

Figure 2: A roll-up of milestones.

Lehnert081709_2

Of course, there’s a lot more to managing a project using Scrum methodology than what I show here. But I hope these examples give you some scheduling ideas for predicting the project’s critical path and monitoring its progress.

Get Weekly PM Insights

Join 50,000+ PMs receiving updates on the latest PM methodologies, PDU opportunities, tool reviews, career tips, and member exclusives.

Protected by reCAPTCHA: Privacy & Terms

PMI ATP
PMI Authorized Training Partner
REP #4082

Learning Paths

PMP® TrainingCAPM® TrainingPgMP® TrainingPMI-ACP® TrainingMS ProjectMS PlannerMS TeamsJira

PM Resources

PDU TrackerLive WebinarsSalary CalculatorTool ComparisonsJob BoardKnowledge BasePM GlossaryOur Faculty

Community

Discussion ForumStudy GroupsEvents Calendar

Follow Us

LinkedInYouTubeTwitterFacebook
MPUGMaster Project User Group

© 2026 MPUG. All rights reserved.

TermsPrivacySitemapAdvertise
Articles

Ask the Experts: When Linking Summary Tasks Makes Sense

Ron from Cleveland, OH asks: Is it a good practice or bad to link summary tasks? Answer: In general I don’t believe that it’s a best practice to link summary […]

3 min read
•over 17 years ago•Updated 10 months ago•
E
Ellen LehnertAuthor
Project Management
Microsoft Project
Best Practices
Productivity
E
Ellen Lehnert

Content Writer

Ellen Lehnert, PMP, Microsoft Project MVP, MCP, is a independent consultant and trainer on Microsoft Project and Project Server. She has taught Microsoft Project over 400 times and is the author of  MS Project 2010 and 2013 published courseware. Ellen is also a contributor and tech editor for many reference books, a developer for the Microsoft Project certification tests and is a frequent meeting speaker for Microsoft, MPUG and PMI. Contact Ellen at ellen@lehnertcs.com.

View all articles by Ellen Lehnert
Related Content

Continue Reading

Discover more insights and articles that complement your current reading

Collaboration challenges in remote projects (and how to fix each one)
Articles
1 min read

Collaboration challenges in remote projects (and how to fix each one)

Discover 5 common remote project collaboration challenges, from knowledge silos to unclear ownership, and learn practical ways to keep teams aligned and work moving.

A
Anonymous
4 days ago
Read
An Introduction to the PMI Practice Standard for Scheduling Conformance Index
Articles
1 min read

An Introduction to the PMI Practice Standard for Scheduling Conformance Index

Learn how the Conformance Index in PMI’s Practice Standard for Scheduling scores a CPM schedule model, and how to assess its components in any scheduling tool.

A
Anonymous
16 days ago
Read
A PM’s Halloween Survival Guide: The Sequel You Didn’t Want but Definitely Need
Articles
1 min read

A PM’s Halloween Survival Guide: The Sequel You Didn’t Want but Definitely Need

Part II of the PM Halloween survival guide takes on shape-shifting requirements and dependencies that won’t stay resolved, with practical defenses for each.

A
Anonymous
about 1 month ago
Read
Explore All Articles