MPUG
D

Dale Howard

Dale Howard is currently a Senior PPM Consultant with Arch Systems, Inc. His hair and beard have turned white because of using Microsoft's project management tools for more than 20 years. Dale started his career using Microsoft Project 4.0 for Windows 95 and began using Microsoft's PPM tools when they introduced Project Central in 2000. Dale is the co-author of 23 books in Microsoft Project, Project Server, and Project Online. He is currently one 0f 26 Microsoft Project MVPs in the entire world and one of only 4 Project MVPs in the United states.

Articles by Dale Howard(10 posts)

Display the Project Summary Task
Article
Latest
Display the Project Summary Task

Background Are you displaying the Project Summary Task in every one of your projects in Microsoft Project? If not, I strongly recommend that you do

D

Dale Howard

Author

November 7, 2022
Create a 5/4-9 Calendar in Microsoft Project
Article
Create a 5/4-9 Calendar in Microsoft Project

Background A number of organizations in the United States, including agencies of the US federal government, use a compressed work schedule to manag

D

Dale Howard

Author

November 1, 2022
Advanced Use of the Nonworking Time Calendar
Article
Advanced Use of the Nonworking Time Calendar

Background In my previous article on Understanding the Nonworking Time Calendar, I showed you how to apply an alternate base calendar as the Projec

D

Dale Howard

Author

October 10, 2022
Make Saturday a Working Day in Microsoft Project
Article
Make Saturday a Working Day in Microsoft Project

Background There was an interesting question recently in the Tech Community Project user forum. A user asked how to change the default working cale

D

Dale Howard

Author

September 6, 2022
Update and Save an Existing Project Template in Microsoft Project
Article
Update and Save an Existing Project Template in Microsoft Project

Background Information I answered a question recently in the Tech Community Project user forum about how to edit an existing enterprise template in

D

Dale Howard

Author

July 6, 2022
Create a Custom Schedule Status Field in Microsoft Project
Article
Create a Custom Schedule Status Field in Microsoft Project

Overview Have you ever tried to use the default task Status field in Microsoft Project? This field uses the Status date that you set in your projec

D

Dale Howard

Author

May 23, 2022
Display Actual Duration in Calendar Days and Not in Working Days
Article
Display Actual Duration in Calendar Days and Not in Working Days

Background Information Last month there was a fascinating “brain teaser” question posted in the Project and Planner User Group on LinkedIn. The use

D

Dale Howard

Author

April 18, 2022
Substituting a Resource in the Middle of a Task
Article
Substituting a Resource in the Middle of a Task

Background There was a really interesting scheduling question posted recently in the Tech Community user forum on Microsoft Project. Although I was

D

Dale Howard

Author

March 21, 2022
Using a Finish By Field Instead of Deadline Dates in Microsoft Project
Article
Using a Finish By Field Instead of Deadline Dates in Microsoft Project

Background Information In my third and previous article in this series, I demonstrated how the use of Deadline dates can negatively impact the Tota

D

Dale Howard

Author

March 1, 2022
How Do Deadline Dates Impact Critical Path Calculations in Microsoft Project?
Article
How Do Deadline Dates Impact Critical Path Calculations in Microsoft Project?

Background Information The other day I had an interesting conversation with a colleague about the impact of Deadline dates on Critical Path calcula

D

Dale Howard

Author

February 21, 2022