Microsoft Project calculates the task start and task finish based on many factors: calendar, constraints, predecessors, resources, lags. (Tip: If you want to see the factors affecting the current task, turn on the Task Inspector, as this Microsoft article explains.) Ever since its first version, Project has provided multiple ways to set the task dependencies — via Predecessors and Successors columns, through the Task Information dialog and in the Task form view:

Predecessors and Successors columns in the Gantt Chart view

Task Information dialog

The Task form view

Each of these options comes with benefits. In the first option, you type the IDs of the tasks the current task is dependent on in the Predecessors column and the same applies to Successor columns too. In the second option, you can see the dropdown with task names to choose the task the current task is dependent on and set multiple predecessors in the Task Information dialog. In the third option you can combine the Task form view with the current view to review as well as change the dependencies set.

Any seasoned Project user might complain that the user interface for setting task dependencies far from intuitive. In option one, you need to type the correct task IDs in the Predecessors or Successors columns and review your work through a Relationship diagram or Network diagram. In options two and three the names in the dropdown are sorted alphabetically and not displayed in the order present in the plan. Another confusion this design adds is that when the plan has many tasks with the same name, there’s no way to know which task is part of which phase. In this example, I don’t know whether the first “Determine project scope” task is part of Scope Phase 1 or Scope Phase 2.

However, rescue is at hand. A new feature was added to Project Online Desktop with the March 2017 version 1703 (Build 7967.2139) release. Thank you, Microsoft.

Let’s review the improvements in this update by examining each option we’ve already covered but as it displays in the new release.

Predecessors and Successors columns in the Gantt chart view

The Task Information dialog

The Task form view

Under the new design when you select a cell in the Predecessors column and then click the down arrow, you’ll see a list of all the tasks in your project. The task hierarchy and order matches your project exactly, making it easy for you to scroll to the right task and then select the checkbox beside it. Ellen Lehnert has published an interesting article on why it’s not a best practice to link summary tasks within a work breakdown structure. The new design moves us a step closer towards avoiding this mistake.

What do you think about it? Tell us in the comments below.

Get Weekly PM Insights

Join 500,000+ PMs receiving updates on the latest PM methodologies, PDU opportunities, tool reviews, career tips, and member exclusives.

PMI ATP
PMI Authorized Training Partner
REP #4082

Learning Paths

PMP® TrainingCAPM® TrainingPgMP® TrainingPMI-ACP® TrainingMS ProjectMS PlannerMS TeamsJira

PM Resources

PDU TrackerLive WebinarsSalary CalculatorTool ComparisonsJob BoardKnowledge BasePM Glossary

Community

Discussion ForumStudy GroupsEvents Calendar

Follow Us

LinkedInYouTubeTwitterFacebook
MPUG Logo

© 2025 MPUG. All rights reserved.

TermsPrivacySitemap
Articles

The New Project: Link Tasks on a Dropdown Menu

Want to learn what’s new in Project 2016? Join author Sai Prasad as he explores updates to the latest versions of Microsoft Project in this MPUG webinar now available on-demand. Microsoft […]

3 min read
•over 8 years ago••
S
Sai PrasadAuthor
Project Management
Microsoft Project
Best Practices
Productivity
S
Sai Prasad

Content Writer

B Sai Prasad, PMP®, PMI-SP®, MVP Project, Senior Manager - Learning & Development, has been with service provider Cognizant Technology Solutions India Pvt. Ltd since 2001 where he was named winner of the company's Global Trainer of the Year award. He has spent 13,000-plus hours in mentoring, coaching, training 9000-plus practitioners on project management topics ranging from project management concepts, project risk management, project scheduling, Microsoft Office Project® to software estimation techniques. He is a Champion of Project Management from PMI India and also Associate Champion Advisory Committee, PMI India. He is awarded the Champion of the Quarter (Q4 – 2012) and Delivery Excellence Award (2011-2012, 2012-2013) from PMI India. He's also the editor of the project management book, Forecast Scheduling with Project 2010. He is a Microsoft Certified Technology Specialist (MCTS) in Project 2010.

View all articles by Sai Prasad
Related Content

Continue Reading

Discover more insights and articles that complement your current reading

Two Project Manager Agent Features You Might Like
Articles
5 min read

Two Project Manager Agent Features You Might Like

Discover two game-changing features of Microsoft’s Project Manager Agent including agent-to-agent communication and the new integrated interface in Planner.

E
Erik van Hurck
about 1 month ago
Read
Master Dependency Analysis in Microsoft Project with SSI Tools!
Articles
2 min read

Master Dependency Analysis in Microsoft Project with SSI Tools!

Learn how to master dependency analysis in Microsoft Project using SSI Tools’ Directional Path, Connecting Path, and Dependency Tracer to analyze predecessors, successors, and project logic.

K
Kenny Arnold
about 2 months ago
Read
A PM’s Halloween Survival Guide
Articles
5 min read

A PM’s Halloween Survival Guide

Discover the spooky parallels between Halloween and project management, from scope creep monsters to ghosted team members, in this fun survival guide for PMs.

R
Ronald B. Smith, MBA, PMP
2 months ago
Read
Explore All Articles