Back to ArticlesBack

Subscribe to our newsletter

Get the latest articles and resources sent straight to your inbox.

MPUG

In the first two articles of this series, a four-step tracking cycle was defined. It includes setting the status date, entering actuals, rescheduling incomplete work, and resource leveling the remaining schedule. This article addresses the third step in the cycle: rescheduling incomplete work.

Do Not Rewrite Project History

The status date defines the time through which project progress has been recorded. Work that was done in the past, prior to the status date, should be recorded in the past. This includes work that was scheduled in the future, but was started early and done in the past. Work that should have been done in the past, but was not, must be rescheduled to be done in the future, after the status date. This ensures that the work is recorded according to when it was performed, not when it should have been performed.

A Simple Example

In the following example, Task A started on 27th of September was marked as 50% Complete as of the October 1st Status Date. The task’s Status is Late, since the cumulative percent duration complete is less than what was planned through the Status Date. In the subsequent status update, on October 8th, the task is marked as 100% complete. However, it appears as if the remaining two days of work were done during the week of September 27th instead of during the week of October 4th.

Figure 1: Task A is only 50% complete when it should be 100% complete as of the Status Date.

 

Figure 2: The remaining work on Task A completed during the second week is erroneously shown as completed during the first week.

We should have rescheduled the incomplete portion of Task A to be completed during the following week, after the October 1st Status Date. To do this, we must check the Split in-progress tasks box in the Schedule Options dialog. This allows us to show that work on the task was interrupted. Then, we use the Update Project dialog to reschedule the incomplete work to start after the current status date (October 1).

Figure 3: Check the Split in-progress tasks box in the Schedule section of the Project Options dialog.

 

Figure 4: Reschedule incomplete work to start after the Status Date using the Update Project dialog.

The result shows the remaining two days of work split and rescheduled to resume on October 4th.  Note that Project considers the task Status to be On Schedule.  The remaining work has been rescheduled into the future and is no longer considered late.

Figure 5: Remaining work rescheduled into the second week, to start after the Status Date.

When the task is marked as 100% complete on October 8th, we see that two days of work were completed in the first week and the remaining two days in the second week.

Figure 6: Work correctly recorded as to when it was performed.

How Do You Find Incomplete Work That Needs to be Rescheduled?

If you use the standard Incomplete Tasks filter, which shows tasks that are not 100% complete, it shows incomplete work in the past and in the future. If you use the standard Late Tasks filter, it shows tasks with a Status of Late, which means that the Cumulative Percent Complete field is not 100% complete by the Status Date.

Figure 7: Task tracking prior to rescheduling incomplete work in the first week.

 

Figure 8: Task tracking after rescheduling incomplete work and marking task 100% complete in the second week.

Filtering for tasks that are not 100% complete and whose Finish dates are less than or equal to the Status Date works, as well. Selecting the Reschedule option across the entire project in the Update Project dialog finds the late tasks for us.

Does it Matter?

Some might argue that rescheduling incomplete work does not matter. If a task is completed prior to the Status Date, it is 100% done, regardless of when the work was completed. To see how earned value calculations are affected by not rescheduling incomplete work, see my prior article on the topic.

Get Weekly PM Insights

Join 500,000+ PMs receiving updates on the latest PM methodologies, PDU opportunities, tool reviews, career tips, and member exclusives.

PMI ATP
PMI Authorized Training Partner
REP #4082

Learning Paths

PMP® TrainingCAPM® TrainingPgMP® TrainingPMI-ACP® TrainingMS ProjectMS PlannerMS TeamsJira

PM Resources

PDU TrackerLive WebinarsSalary CalculatorTool ComparisonsJob BoardKnowledge BasePM Glossary

Community

Discussion ForumStudy GroupsEvents Calendar

Follow Us

LinkedInYouTubeTwitterFacebook
MPUG Logo

© 2025 MPUG. All rights reserved.

TermsPrivacySitemap
Articles

Rescheduling Incomplete Work As Part of a Project’s 4-Step Tracking Cycle

In the first two articles of this series, a four-step tracking cycle was defined. It includes setting the status date, entering actuals, rescheduling incomplete work, and resource leveling the remaining […]

4 min read
•almost 4 years ago••
R
Robin NicklasAuthor
Project Management
Microsoft Project
Best Practices
Productivity
R
Robin Nicklas

Content Writer

Robin Nicklas is a project management consultant and educator. Since 2001, he has trained project managers in the aerospace, financial, telecommunications, government, and software sectors. Prior to teaching, he spent twenty years in information systems and technology, twelve of which he managed software development at large information service companies. Since 2003, he has taught graduate and undergraduate courses in project management at the University of Washington in Seattle, as well as MS Project courses at Bellevue College Continuing Education since 2011. Robin is a former president of the PMI Puget Sound Chapter in Seattle and a certified PMP. He can be contacted through his website, robinnicklas.com.

View all articles by Robin Nicklas
Related Content

Continue Reading

Discover more insights and articles that complement your current reading

Two Project Manager Agent Features You Might Like
Articles
5 min read

Two Project Manager Agent Features You Might Like

Discover two game-changing features of Microsoft’s Project Manager Agent including agent-to-agent communication and the new integrated interface in Planner.

E
Erik van Hurck
about 1 month ago
Read
Master Dependency Analysis in Microsoft Project with SSI Tools!
Articles
2 min read

Master Dependency Analysis in Microsoft Project with SSI Tools!

Learn how to master dependency analysis in Microsoft Project using SSI Tools’ Directional Path, Connecting Path, and Dependency Tracer to analyze predecessors, successors, and project logic.

K
Kenny Arnold
about 1 month ago
Read
A PM’s Halloween Survival Guide
Articles
5 min read

A PM’s Halloween Survival Guide

Discover the spooky parallels between Halloween and project management, from scope creep monsters to ghosted team members, in this fun survival guide for PMs.

R
Ronald B. Smith, MBA, PMP
about 2 months ago
Read
Explore All Articles