The following in an excerpt from chapter 4 of Microsoft® Project Do’s and Don’ts by Sam Huffman. Part of the MPUG Essentials Training. Download full version of chapter 4.

Once the outline is entered in Microsoft® Project, you are ready to estimate and enter task durations. This is accomplished by typing the estimated duration in minutes, hours, days, weeks or months into the Duration field:

  • 1m = 1 minute;
  • 1h = 1 hour;
  • 1d = 1 day;
  • 1w = 1 week; and
  • 1mo = 1 month

In Project, duration is a measure of working time, not sequential or calendar time. This means a week is five days. If a task is started on a Friday, it is concluded on the following Thursday since weekends are not working time by default. The default duration is set for days.

Figure 4.1: The Duration column is a field. It indicates the span of working time for a task. On a summary task it is the span of working time from the start of the earliest sub-task to the finish of the latest.

Milestones are zero duration tasks that point out a date in the schedule. No resources are assigned to this type of task in Project. In the schedule, they have the appearance of a diamond, not a bar. One use of a milestone is to denote the end of a phase. Another example is to denote a time in the schedule when a report is due.

Figure 4.2: Milestones have no duration.

Before assigning durations to tasks, you need to understand the relationship of all the task schedule variables and how they inter-relate.

   

Do This: At this point, carefully consider changing your scheduling mode to Automatically Schedule. Let Project figure out the finish dates dynamically.

 

Don’t Do This: Don’t enter a start or finish date for a task in the early stages of creating the project file. Project understands this to be a manual override to calculations and will constrain the task. This hinders dynamic scheduling.

 

Want more? Download a free preview of Chapter 4: Enter Task Durations or buy the book.

Visit mpugwp.wpengine.com/do for more information.

Get Weekly PM Insights

Join 500,000+ PMs receiving updates on the latest PM methodologies, PDU opportunities, tool reviews, career tips, and member exclusives.

PMI ATP
PMI Authorized Training Partner
REP #4082

Learning Paths

PMP® TrainingCAPM® TrainingPgMP® TrainingPMI-ACP® TrainingMS ProjectMS PlannerMS TeamsJira

PM Resources

PDU TrackerLive WebinarsSalary CalculatorTool ComparisonsJob BoardKnowledge BasePM Glossary

Community

Discussion ForumStudy GroupsEvents Calendar

Follow Us

LinkedInYouTubeTwitterFacebook
MPUG Logo

© 2025 MPUG. All rights reserved.

TermsPrivacySitemap
Articles

Microsoft Project Do’s and Don’ts: Enter Task Durations

The following in an excerpt from chapter 4 of Microsoft® Project Do’s and Don’ts by Sam Huffman. Part of the MPUG Essentials Training. Download full version of chapter 4. Once the outline is entered […]

2 min read
•about 8 years ago••
S
Sam HuffmanAuthor
Project Management
Microsoft Project
Best Practices
Productivity
S
Sam Huffman

Content Writer

Sam Huffman first gained insight into Microsoft Project while working as a member of the MS Project development and support team. He has maintained his depth of knowledge of MS Project with each release and is a leading authority in the use and features of MS Project, Project Server and Project Online. Since the early 1990's Sam has honed his instruction skills by delivering training programs to thousands every year. Sam is a frequent content contributor to the Microsoft Project User Group (MPUG) and speaks to groups often about MS Project, Enterprise Project Management and the discipline of Project Management. He was awarded Microsoft Most Valuable Professional from 2010-2017. Check out his blog on MS Project. The softcover version of my newest book Microsoft® Project Do’s and Don’ts is now available for purchase! It is portable, brief and to the point so you can find help when you need it. Through tips, best practices and examples it will help you jumpstart your project!

View all articles by Sam Huffman
Related Content

Continue Reading

Discover more insights and articles that complement your current reading

Two Project Manager Agent Features You Might Like
Articles
5 min read

Two Project Manager Agent Features You Might Like

Discover two game-changing features of Microsoft’s Project Manager Agent including agent-to-agent communication and the new integrated interface in Planner.

E
Erik van Hurck
about 1 month ago
Read
Master Dependency Analysis in Microsoft Project with SSI Tools!
Articles
2 min read

Master Dependency Analysis in Microsoft Project with SSI Tools!

Learn how to master dependency analysis in Microsoft Project using SSI Tools’ Directional Path, Connecting Path, and Dependency Tracer to analyze predecessors, successors, and project logic.

K
Kenny Arnold
about 1 month ago
Read
A PM’s Halloween Survival Guide
Articles
5 min read

A PM’s Halloween Survival Guide

Discover the spooky parallels between Halloween and project management, from scope creep monsters to ghosted team members, in this fun survival guide for PMs.

R
Ronald B. Smith, MBA, PMP
about 2 months ago
Read
Explore All Articles