Tools which generate S-Curve to track schedule performance / forecast?

Home Forums Discussion Forum Tools which generate S-Curve to track schedule performance / forecast?

Viewing 1 reply thread
  • Author
    Posts
    • #116143
      Anonymous
      Inactive

      Does anyone know if there are add on tools which can take data from MS Project and generate an S-Curve to track schedule performance and schedule forecast? Specifically, track and calculate schedule variances using actual start, actual finish versus baseline start and baseline finish dates. Additionally, track number of actual “inch-stones” completed against baseline and all actual “inch-stones” completed. In this context “inch-stones” refers to each actual start and actual finish in a schedule.

    • #125448

      Hello Paul,

      http://www.ProjectProCorp.com. offers an S Curve Add In tool. Give it a try they offer a Trail edition.

      Regards,

      Matt