Hi to all,
i would like to ask if is possible to format the text of task bar in team planner view as below request.
Example:
Paul is assigned to “Task1” that is under summary task “Project 1”.
In planner view i see written on the task bar “Task1”
If i go on format and select Roll Up level 1, the bar text changes in “Project 1”
Is there a way to see Roll Up level 1+2 in the bar, for instance : Project 1 – Task1 ??
I think it will be more clear the assignment of every resource.
Many thanks
Francesco