tasks interdependence-MS Project 2016

Home Forums Discussion Forum tasks interdependence-MS Project 2016

Viewing 4 reply threads
  • Author
    Posts
    • #417707
      Stergios Kokkoris
      Guest

      Dear friends and colleagues,

      I have the below issue:

      There is a task A that lasts, for example, 8 working days as well as the taks B that lasts 7 working days.

      The task A can not be completed if a part of the task B hasn’t be finished first. The duration of partial completion of task B is 2 working days.

      The task A can start any time but during its evolution needs the information of the partial completion of task B in order to continue its evolution and be completed.

      How can this interdependence be represented in a Gantt Chart?

      Thank you in advance for your help.

      Stergios Kokkoris
      Civil Engineer

    • #417709
      Anonymous
      Inactive

      You have a couple of constraints that make setup a bit difficult. You could split both tasks into two tasks each (Task A1, Task A2, Task B1, Task B2) and then setup appropriate predecessors. You may also need a FF predecessor type. Of course there is a balance between complicating task setup and proper team communication. Just saying if that is the only task in question.

    • #417712
      Daryl Deffler
      Guest

      Stergios
      Try making the dependency relationship Start-Start and also add a positive Lag value. Meaning, you could link Task B as the predecessor to Task A the successor with a Start Start relationship and add a +2D (plus two days) Lag value. This essentially says both A and B can start at the same time but delays the scheduled start of A (the successor) 2 days.

      Just a thought.
      Hope that helps.

    • #417713
      Thomas Boyle
      Guest

      Stergios, This is a trick question, and you’ve left out a key piece of information. You’ve said that A can start at any time but needs 2 days of progress on B before it can “continue its evolution and be completed.” How much of its “evolution” depends on the information from B? In the simplest case, A can’t finish until 2 days after B starts. I.e. B>SF+2>A. This (two uninterruptible tasks with SF relationship) is a situation that virtually never happens in real life. I’d avoid it. Better follow Larry’s advice and break the tasks up. E.g. two alternatives:

      1 Alt 1 8 days
      2 SMS 1 0 days
      3 Task A 8 days 4SF+2 days,2
      4 Task B 7 days 2
      5 Alt 2 8 days
      6 SMS 2 0 days
      7 Task A Execution 8 days 6
      8 Task A Completion 0 days 7,9
      9 Task B Phase 1 2 days 6
      10 Task B Phase 2 5 days 9

      Good luck, tom

    • #417714
      Stergios Kokkoris
      Guest

      Dear Lary, Daryl, and Thomas thank you very much for your contribution. I appreciate your time and effort.

      Warmest regards

      Stergios Kokkoris

Viewing 4 reply threads
  • You must be logged in to reply to this topic.