      In MS Project 2016, my status date bar isn’t showing up. I’ve picked the color and the “type” and nothing shows.

    • #411704
      Anonymous
      Inactive

      A couple of obvious questions to start. Did you create a status date, and if so is it the day before the current date? The status date line shows at the end of the day vs. today’s date that shows in the beginning, and can overlap the status date if they conflict. It’s also only for the view you set it for, not all views. Hope that helps.

    • #411705

      That’s it! You solved it. I had them on the same date – which is rare but it happened. I now have a status bar. Thank you!