      some of my task do not have the correct duration calculated not all of them does anyone know what is causing this?

    • #416208
      Anonymous
      Inactive

      Hi Bill, that can be due to calendar changes. Are you using multiple calendars for tasks/resources?

    • #416398

      Do you have resources assigned to summary tasks? They should only be assigned tot he lowest levels.