Home › Forums › Discussion Forum › Problem with MS Project 2016 -cannot move tasks
I have a virtual machine instance of MS Project 16 running on a Windows 10 instance on my MAC.
I have set up the gantt chart with fields for planned start and planned finish, and actual start and actual finish.
When I created the tasks they were manual only. Then I switched to automatic and added a planned start and finish date and then updated the percent work complete to 100% the actual start and finish still remain NA. Why?