Home › Forums › Discussion Forum › Outline code issues Project Server to standalone project
Tagged: Lookup Table
Hello,
I really could use some help.
I created outline code in Project Professional standalone.
Then sent it to Project Enterprise.
I was using it on my Computer through professional but stored on the server without issue.
Then I created MPP files and the outline code shows up nicely. When the MPP files are opened on a standalone Project Professional. Then the Outline codes are missing.
Any help is appreciated.
Regards,
Matt
After a few hours of looking and testing I now learned that MS Project Server doesn’t allow Look up tables or it’s values to transfer to individual mpp files.
Does this not defeat the purpose of an enterprise? Or is there a work around available?