Home › Forums › Discussion Forum › MS Project Pro 2019 — Start and Finish Variance results are incorrect
I get these incorrect variances in line 1 below. I’ve added a new “Test” task and it calculates correctly.
Baseline Start Start Start Variance Baseline Finish Finish Finish Variance
Line 1 GO-LIVE Release 1 11/8/19 11/19/19 30 days 11/10/19 11/21/19 30 days
Line 2 Test Go-Live Task 11/8/19 11/21/19 7 days 11/10/19 11/21/19 7 days
Has anyone seen something like this?