MS Project 2013 *Enterprise* Permissions

Home Forums Discussion Forum MS Project 2013 *Enterprise* Permissions

  • This topic has 1 reply, 2 voices, and was last updated 7 years ago by Anonymous.
Viewing 1 reply thread
  • Author
    Posts
    • #413363
      Mike Chrepta, PMP
      Guest

      Can a role, “Project/Program/Portfolio Manger” have *only* read rights on the server-schedule(s), but still have the ability to approve work/hours on PWA? – Thanks!

    • #413364
      Anonymous
      Inactive

      Mike, the basic answer is no. You need edit rights to apply the updates on the project, and for the ability to be a Status Manager to associated tasks. Now with that said, could someone start with edit permissions, become the Status Manager on tasks, subsequently have that permission removed, and still be able to approve work in PWA? To be honest I’m not sure. That would be a good test. But, if he/she can I would (1) consider that a bug, and (2) not the ideal scenario. Maybe someone has an answer, but hope that makes sense.

Viewing 1 reply thread
  • You must be logged in to reply to this topic.