Home › Forums › Discussion Forum › Making Due-Date Fall Prior to Weekend, Not After?
Hi,
In my file if something is due on a date that is a non-working day, it shifts to being due the next working day. Is there a way to program it so that these things are due the prior working day (when the real due date falls on a non-working day)?
Thanks,
Daniel
Good question and I can understand the request. Sorry Daniel, that’s the behavior of Microsoft Project.