Linking task across project

Home Forums Discussion Forum Linking task across project

Viewing 1 reply thread
  • Author
    Posts
    • #413277
      guy forget
      Participant

      I created a consolidated projects files by grouping three projects.
      Ex: I created a start to finish link between tasks of 2 projects. Link is there but the successor task stays were I was. In other words the finish date one task in project 1 will become the star date of another task in project 2.
      I was expecting that start date of project 2 would change based on the link a made.
      What should I do so that start date of project 2 following link a made.

    • #413280
      Anonymous
      Inactive

      Links between projects affect successor tasks only, not the project itself. You need to go to Project Information to set the project start date. Hope that helps…

Viewing 1 reply thread
  • You must be logged in to reply to this topic.