      I am trying to figure out how to share resources between different team members. Each team member has their own set of projects, so I would like for them to be able to choose resources from the same “pool”, so I can compile all the projects in a Master MS Project file, and evaluate resources accordingly. The issue I am having is my coworkers cannot access the MS Project Resource file that I created.
      When they go to Resources > Resource Pool > Share Resources, the resource file does not show up. Does anyone know how to do this?

      Thanks!

    • #417330
      Anonymous
      Inactive

      The PM needs to have both their project and the resource pool open in order to initiate a share. Does that help?