How can I transfer data from custom cost column to fixed cost

Home Forums Discussion Forum How can I transfer data from custom cost column to fixed cost

Viewing 1 reply thread
  • Author
    Posts
    • #400150
      Guy Forget
      Guest

      I added 4 custom cost columns, one of which show the total of 3 others. How can I transfer data from that customized column to fixed cost column for the 300 tasks of my project.
      Thanks for your help!
      Guy

    • #400153
      Anonymous
      Inactive

      Guy, you should be able to copy the entire total cost column and then select and paste it to the Fixed Cost column. Hope that helps…