How can I add/include the %Complete progress bar in a summary task?

Home Forums Discussion Forum How can I add/include the %Complete progress bar in a summary task?

  • This topic is empty.
Viewing 5 reply threads
  • Author
    Posts
    • #406514

      In earlier versions of MsProject I could show a bar under the roll-up summary task to visually show where the progress is at. It was particularly useful when showing the plan in the Outline 2/3 view

    • #406515
      Jigs Gaton
      Guest

      Edgardo, you can edit the summary task display to show %xxx complete. Will that work for ya?

    • #406516

      I know how to show the % Complete as a number (left or right of a summary task). What I am interested is a progress bar showing underneath the summary task bar

    • #406517
      Anonymous
      Inactive

      Edgardo, are you asking about a progress bar in the Gantt chart? I don’t remember any version that shows a progress for summary tasks, but you can add that to the Gantt view by using the Bar Styles option. Go to the Format ribbon, Format, Bar Styles. Copy the current Progress Bar style to a new line under the existing styles, and enter the contents of the Show For…Tasks similar to the Summary Task or Manual Summary task. Hope that helps…

    • #406518

      Great, Thanks Larry! I found that you also need to change the “To” setting (right column) to % Complete. With this a progress bar is being shown across the summary task with the % complete

    • #406520
      Anonymous
      Inactive

      You are welcome, glad it helped…