History Timesheets disabled

Home Forums Discussion Forum History Timesheets disabled

Viewing 1 reply thread
  • Author
    Posts
    • #378225
      Paul Lor
      Guest

      Hi!

      In the Approvals section in PWA on the option for Approvals -> Navigate -> History -> Timesheets is disabled. I want to see the previously approved timesheets. How do I do it?

      Thanks!

      Best regards

    • #378234
      Anonymous
      Inactive

      Paul, that can be a tough one to diagnose without a little digging in. Does this happen with all approvers? What about administrators vs. Resource Managers? Try temporarily giving a Resource Manager administrator permissions and see if this lights up the option. Just trying to see if it is a permission setting? Are the resource managers setup in the Timesheet Managers list (under the Time and Task Management permission settings group). Let me know what you find out with any of these. Thanks…

Viewing 1 reply thread
  • You must be logged in to reply to this topic.