Home › Forums › Discussion Forum › EAC Costs not rolling up properly
Tagged: Mike
I have re-planned future tasks now that definition is better known. My EAC does not change after I have added the revised scope.
I have not yet re-baselined the project as I need to provide new EAC forecast for mgmt approval.