Duration based on resource capacity

Home Forums Discussion Forum Duration based on resource capacity

  • This topic is empty.
Viewing 0 reply threads
  • Author
    Posts
    • #485344
      Robert Holguin
      Participant

      How do I get project to adjust duration based on resource available capacity? Example, I have a task with work effort set at 8hrs, however my resource is only available 20% of the 8hr day, 2hrs per day. Project should set duration as 4days but it doesn’t.

Viewing 0 reply threads
  • You must be logged in to reply to this topic.