duplication of a repeating series of tasks

Home Forums Discussion Forum duplication of a repeating series of tasks

  • This topic has 0 replies, 1 voice, and was last updated 10 years ago by Arne Gronningsater.
Viewing 0 reply threads
  • Author
    Posts
    • #321781
      Arne Gronningsater
      Guest

      I have a schedule where the work flow on one building is repeated in 7 subsequent and similar buildings. How do I copy and paste such that cell values (task predecessors) are relative and not absolute, i.e. that they are in relationship to the building they are in and not the first building?
      Thanks,
      Arne

Viewing 0 reply threads
  • You must be logged in to reply to this topic.