Does Std Calendar Need to be set up before adding resources/projects?

Home Forums Discussion Forum Does Std Calendar Need to be set up before adding resources/projects?

Viewing 4 reply threads
  • Author
    Posts
    • #370037
      John Murphy
      Member

      I tried to setup the calendar and got this error … Project Web App 2016 preview feature requires at least MS IE 8.0.

      I am using IE 8.0 and expect to get IE 11 soon.

      I have sync’d in resources and have added ONE project to my PWA instance.

      I have now read in the MS ProjectExpert Admin book that you should configure your organization’s enterprise calendar and create new base calendars before adding resources or projects.

      Do i need to remove all resources including generic ones I created and the one projects? This does not seem logical given you should be able to create a new calendar or edit the enterprise std one any time.

      Guidance is needed … Thanks
      John

    • #370049
      Anonymous
      Inactive

      If you will be using the out of box standard calendar you shouldn’t have to worry. You can set it up when you can.

    • #370121
      John Murphy
      Member

      Larry,

      Thanks for the quick reply.

      Yes at the moment the resources and projects are all US ones.

      However, I will be adding in India GOC resources. When I import the India GOC team, I plan to switch them to the India calendar via Bulk Edit. Does it matter whether the India calendar is setup before I load the resources?

      thanks
      John

    • #370157
      Anonymous
      Inactive

      John, I haven’t tried it but calendars and resources will change continually and I’ve never heard of any problems on what you are trying to do. Best I can give you, but not everyone reads the golden book and they build calendars just fine. I would assume the dependency is all about process and not constraint. Good luck…

    • #373867
      John Murphy
      Member

      Thank you!