Custom field to block book multiple resources based on location?

Home Forums Discussion Forum Custom field to block book multiple resources based on location?

Viewing 2 reply threads
  • Author
    Posts
    • #392189
      Danny Humphries
      Guest

      I have multiple resources within multiple buildings, for example assets 1 thru’ 4 in building 1, 5 thru’ 10 in building 2 etc. I’ve filled the resource sheet with the assets as the resource name and building number as a custom field (text3).
      I’m looking to make assets unavailable when the building is taken out of service (statutory inspections etc.) i.e. the inspection task overrides asset tasks or at least shows a conflict on the timeline for example.
      Ideas? or preferably solutions 🙂

    • #392224
      Anonymous
      Inactive

      Danny, try creating a calendar for each building, assign that calendar to each of the resources for those buildings, and then setup non-working time for when the building is out of service. Does that sound like it might help?

    • #392304
      Danny Humphries
      Guest

      I’ll give that a try and let you know how I get on, thanks for the input

Viewing 2 reply threads
  • You must be logged in to reply to this topic.