Home › Forums › Discussion Forum › Clear Actual Data and Dates to Rebaseline
Tagged: Clear dates
I have been working in a schedule for several months, making updates and modifying some logic and durations as thing change on the project. I would like to create a new baseline based on these changes, but not with any actual dates I have been entering along the way. What’s the best way to do this? I thought if I can clear all the actual start and finish dates I would “reset” the orignal schedule, however, there still appears to be work showing as completed, it only shows up in the summary bars. Any ideas?